In Business Environment Bow Lane Limited v Deanwater Estates Limited [2009] EWHC 2014 (Ch), the Court of Appeal had ordered the tenant to pay the landlord’s costs of a preliminary issue, which the tenant won at first instance but lost on appeal. The claim was ultimately settled for a nominal sum, with the trial judge finding that the landlord had grossly exaggerated the claim and ordering it to pay the tenant’s costs on an indemnity basis. On the assessment of the landlord’s preliminary issue costs, the costs judge disallowed them entirely, holding that they were unreasonably incurred in light of the claim’s exaggerated nature. The High Court allowed the landlord’s appeal, finding that the Court of Appeal’s costs order was a self-contained decision that had to be given effect to and assessed based on reasonableness within the context of the preliminary issue alone, irrespective of the claim’s ultimate outcome or findings of exaggeration. The landlord relied on Cope v United Dairies [1963] 2 QB 33, in which it was held that an assessing tribunal must carry out the assessment as directed by the previous court, and cannot refuse to do so because it considers the order to be wrong.
“The citations from the modern Court of Appeal cases extracted above, and Cope, make it clear that the important thing to do is to construe the order. If the effect of the order is that it was intended to take effect whatever the outcome of the action, then the Master’s order was wrong. He should have assessed the costs of the issue, by reference to their reasonableness and propriety within the issue, but not by reference to the ultimate fate of the action, no matter how misconceived it might have been. It is the duty of the assessing tribunal to carry out the assessment which the previous court has directed it to carry out.”
BUSINESS ENVIRONMENT BOW LANE LIMITED V DEANWATER ESTATES LIMITED [2009] EWHC 2014 (CH)
The underlying claim in Business Environment Bow Lane Limited v Deanwater Estates Limited involved a dispute over a dilapidations claim under a lease. The lease was terminated in December 2004, and in April 2005, Business Environment, the new landlord, served a schedule of dilapidations valued at around £416,000 on Deanwater, the former tenant.
Deanwater believed it had a complete defence based on a previous collateral contract and/or promissory estoppel. It was ordered that the existence of this defence be tried as a preliminary issue.
In December 2006, the judge found in favour of Deanwater and dismissed the action. However, in June 2007, the Court of Appeal reversed this decision and ordered Deanwater to pay Business Environment’s costs of the appeal and the hearing of the preliminary issue.
Chronology of relevant events
Issues to be decided
The key issue was whether, on assessment of Business Environment’s costs that Deanwater was ordered to pay by the Court of Appeal in relation to the preliminary issue, the costs judge could assess those costs at nil on the basis that they were unreasonably incurred because the dilapidations claim as a whole had been grossly exaggerated, as found by the trial judge when making a final costs order in Deanwater’s favor.
In other words, could the costs judge effectively undermine the Court of Appeal’s prior costs order based on the ultimate outcome of the claim, or was he bound to assess the reasonableness of the preliminary issue costs within the context of that issue alone, without regard to the claim’s overall fate?
Parties’ positions and arguments
Business Environment argued that:
Deanwater argued that:
Decision
The High Court allowed Business Environment’s appeal and overturned the costs judge’s assessment at nil. The key points in its reasoning were:
“The citations from the modern Court of Appeal cases extracted above, and Cope, make it clear that the important thing to do is to construe the order. If the effect of the order is that it was intended to take effect whatever the outcome of the action, then the Master’s order was wrong. He should have assessed the costs of the issue, by reference to their reasonableness and propriety within the issue, but not by reference to the ultimate fate of the action, no matter how misconceived it might have been. It is the duty of the assessing tribunal to carry out the assessment which the previous court has directed it to carry out.” [29]
“In the circumstances I think that the Master erred in his approach. He was not entitled to consider that the claimant’s costs of the preliminary issue were unjustified because the claim turned out to be exaggerated and they would not have been incurred if it had not been. That is saying no more than the action was ultimately lost. He should have determined the costs of the preliminary issue by looking at the reasonableness of their being incurred, and the conduct of the parties under CPR 44.5(a), in relation to that issue, and not by reference to what happened in the action at the end of the day.” [41]
In conclusion, the Court held that the costs judge erred in disallowing the preliminary issue costs based on the claim’s exaggerated nature as a whole. Those costs had to be assessed by reference to their reasonableness and the parties’ conduct in relation to that preliminary issue alone. The matter was remitted back to the costs judge to carry out the assessment on that correct basis.
Subscribe to our Newsletter
By signing up you consent to receiving occasional emails about our latest news and services. Your information will be used in accordance with our privacy policy.
Aaron v Shelton [2004] EWHC 1162
Booth v Britannia Hotels Limited [2002] EWCA Civ 579
Collier v Williams [2006] EWCA Civ 20
Cope v United Dairies [1963] 2 QB 33
Koshy v Deg-Deutsche Investitions [2003] EWCA 1718
Lahey v Pirelli Tyres Ltd [2007] EWCA Civ 91
Lloyds Investments (Scandinavia) Ltd v Ager-Hanssen [2003] EWHC 1740
Northstar Systems v Fielding [2006] EWCA 1660
Re Uddin [2005] 1 WLR 2398
DILAPIDATIONS CLAIM | PRELIMINARY ISSUE | COURT OF APPEAL | COSTS ORDER | ASSESSMENT OF COSTS | REASONABLENESS | EXAGGERATED CLAIM | CONDUCT OF PARTIES | CPR 44.3(1) | CPR 44.3(4)(a) | CPR 44.5(2) | CPR 44.5(3)(a) | CPR 3.1(7) | INDEMNITY BASIS | COLLATERAL CONTRACT | PROMISSORY ESTOPPEL | STATEMENT OF TRUTH | SCOTT SCHEDULES | PRE-TRIAL REVIEW | MR JUSTICE MANN | MASTER GORDON-SAKER | BOOTH V BRITANNIA HOTELS LIMITED | LAHEY V PIRELLI TYRES LTD | NORTHSTAR SYSTEMS V FIELDING | COPE V UNITED DAIRIES | LLOYDS INVESTMENTS (SCANDINAVIA) LTD V AGER-HANSSEN | KOSHY V DEG-DEUTSCHE INVESTITIONS | COLLIER V WILLIAMS | AARON V SHELTON | RE UDDIN