Background
These proceedings concern a complex construction dispute involving multiple defendants related to alleged defects in student accommodation constructed using modular building techniques. The claimants, GS Woodland Court GP 1 and GP 2 Limited, acting as general partners for GS Woodland Court Limited Partnership, brought proceedings against seven defendants involving significant allegations concerning fire safety attenuation and construction defects.
The construction was managed on a construction-management basis, with seven defendants spanning different aspects of the project: the construction manager, architect, cladding contractor, modular unit supplier, developer, fire-stopping works contractor, and installer. The claim involved allegations that numerous fire safety defects had not been properly implemented in the modular accommodation.
A half-day Costs Management hearing was convened to assess and manage the litigation costs, during which an unusual application was made by several defendants for their costs of the Costs Management hearing itself. The total claim against the defendants was approximately £11 million, with potential remediation costs estimated at £30 million.
Costs Issues Before the Court
The primary costs issues before the court included:
1. Assessment of the reasonableness and proportionality of the claimants’ costs budget
2. Evaluation of the claimed hourly rates against guideline rates
3. Consideration of the defendants’ application for costs of the Costs Management hearing
4. Determining an appropriate approach to costs management in multi-defendant construction litigation
The Parties’ Positions
The claimants (represented by Ms Packman KC) argued that the complexity of a multi-defendant case justified their approach. They initially sought a costs budget of £8.74 million, which was subsequently reduced to approximately £7.4 million.
The defendants (particularly represented by Ms Stephens KC) contended that the claimants’ costs were disproportionate and unreasonable. They highlighted significant discrepancies between the claimed rates and the Guideline Rates, with the claimants’ solicitors charging substantially higher rates without meaningful justification.
The Court’s Decision
Mr Justice Constable made several critical observations:
1. Rates: The claimed rates significantly exceeded Guideline Rates, with Jones Day charging rates substantially higher than recommended. The court indicated a potential downward adjustment of approximately £1.4 million solely based on rate reductions.
2. Proportionality: While acknowledging the case’s complexity, the judge suggested the claimants’ costs were potentially disproportionate, particularly when compared with the defendants’ aggregate costs.
3. Costs Management Hearing: Applying recent authorities (Nicholas Worcester v Dr Philip Hopley and Jenkins v Thurrock Council), the court determined that the claimants’ unrealistic initial budget warranted potential cost consequences.
4. Final Outcome: The court approved a reduced budget of £4.212 million for estimated costs and granted the defendants’ application for costs of the Costs Management hearing, with D2, D3, and D4/D5 recovering their reasonable attendance costs from the claimants.















