In Rudan Business Holding SA v Tridan Trusted Advisors AG & Ors [2025] EWHC 3565 (Ch), the High Court refused to treat a single revised costs budget filed shortly before the first effective further CCMC as prompt for phases whose costs had long been incurred. The judgment restates that costs management is concerned with future costs, and that late revision turns budget approval into something closer to a summary assessment. Parties who defer revisions risk failing the promptness threshold altogether.
Background
The petitioner presented an unfair prejudice petition under section 994 of the Companies Act 2006 concerning a company it owned equally with the first respondent [2], [4]. Deputy ICC Judge Lambert approved the respondents’ costs budget on 21 March 2022 and the petitioner’s on 28 April 2022 [7].
The respondents served an Amended Defence and Counter-Petition on 12 May 2022, and the petitioner served its Amended Reply on 9 August 2022 [8], [9]. On 2 February 2023 the trial was vacated and a Further CCMC ordered [12]. Letters of Request to the Swiss court followed, and the Further CCMC was adjourned twice before it was effective on 6 May 2025 [15], [17], [21].
The respondents served a revised budget on the petitioner in January 2023 but it was never filed [11]. The petitioner filed its revised costs budget on 29 April 2025 and the respondents sent theirs on 30 April 2025 [20]. Consideration of the budgets was adjourned to 18 December 2025 [21].
Costs Issues Before the Court
Both parties applied under CPR 3.15A to vary their approved budgets, and the judge decided the principle of variation but not quantum [1]. A revising party had to satisfy two threshold requirements: a significant development warranting revision, and prompt submission of the particulars to the other parties and the court [27]. Only then could the court exercise its discretion [26]. The promptness question was whether parties who had deferred revision to the Further CCMC had acted promptly [82], [86].
The Parties’ Positions
Mr Griffiths, for the petitioner, submitted that promptness depended on the circumstances. Both sides knew by January 2023 that their budgets needed amending and understood that revised costs would be dealt with at a Further CCMC, while the proceedings were effectively paused for the Swiss process [82]. Serving one revised budget before the effective Further CCMC was sensible and proportionate and caused no prejudice [83].
Ms Page, for the respondents, accepted that context mattered but argued that the primary purpose of costs budgeting is to budget for future costs, and that parties must deal with significant developments as they arise [84]. She said the petitioner had waited nearly three years, and that promptness lets the parties and the court understand how a particular development affects costs [86]. Her primary case was that the respondents’ January 2023 budget was prompt [85].
The Court’s Decision
The judge began from CPR 3.12 and 3.15: the primary function of the court is to manage costs to be incurred, so costs management is concerned with approving future budgeted costs, not incurred costs [24]. Following Persimmon Homes Ltd v Osbourne Clark LLP, he accepted that a direction to approve only future costs has a degree of unreality, because work continues after budgets are filed, and that CPR 3.15A(6) was introduced to meet that problem [25].
CPR 3.15A(6) is, however, to be interpreted having regard to the threshold requirement of promptness. The judge stated that it does not give a party licence to delay service or submission of a revised costs budget until after costs have been incurred [25]. He set out Master Kaye’s reasoning in Persimmon that the rule “was never intended to and is not open season to come back and vary a costs budget after the event” [25].
Master Kaye’s further view, as set out by the judge, was expressed with caution. She was not currently persuaded that there would be jurisdiction to approve a variation for a phase whose costs had been fully incurred before the application to vary was made. Such costs would either turn on whether there was good reason to depart from the last approved budget or be at large, for the costs judge in due course [25].
Master Kaye had treated promptness as mandatory and dependent on context, the purpose of budgeting being to control recoverable costs prospectively [33]. The judge agreed that promptness is judged in context, but did not accept that context excused the parties from revising their budgets until before the first effective Further CCMC on 6 May 2025. The primary role of the court is to manage prospective costs; costs budgeting is not to approve incurred costs [87].
A party facing a significant development must promptly revise its budgeted costs for that development, even if this produces several revisions over time [88]. That allows the other party and the court to see what additional costs are predicted for the particular development. Late revision on incurred costs defeats the purpose of budgeting and, in the judge’s words, “changes the function of the court from approving predicted budgeted costs to carrying out a task which is more akin to a summary assessment of costs” [88].
The respondents’ January 2023 budget did not assist them. It was served on the petitioner but never filed, no application was made in respect of it, and its appearance in an exhibit to a security for costs witness statement was not submission to the court [89]. Even had it been relied on, it was served nearly eight months after the Amended Defence [92].
For statements of case, the parties should have prepared revised budgeted costs shortly after the Amended Defence, before the costs were incurred or fully incurred. Revision nearly three years later could not on any interpretation be prompt [91]. The judge observed that the respondents’ two budgets showed the difficulty of approving incurred costs, the sum sought rising from £114,299 to £185,784 without explanation [92].
By 20 January 2023 both parties had completed the disclosure exercise and incurred its costs, so revised disclosure costs should have been submitted before then [95], [96]. The parties had known the extent of the factual disputes since August 2022, and should have estimated the increased witness statement costs between then and 20 January 2023 [97].
By contrast, both parties acted promptly for the Further CCMC, whose issues would only have emerged in correspondence before it [93], and for trial preparation and trial, which could not be properly assessed until that hearing approached [98]. Increases for those three areas were allowed in principle, with quantum yet to be decided [99].
Practical Implications
This is a first instance decision of a Deputy ICC Judge applying Persimmon. A party facing a significant development should prepare and submit revised budgeted costs for that development promptly, before the costs are incurred or fully incurred, rather than accumulate developments for a later CCMC [88], [91]. A shared understanding that revisions would be dealt with at a Further CCMC did not excuse delay here [82], [87].
Service on the other side is not enough. The particulars must also be submitted to the court; serving a draft on the opponent, or exhibiting it to evidence on another application, did not count [89]. Each revised costs budget should be tied to the development it addresses, so that the opponent and the court can see what each increase relates to [88].
Practitioners opposing a variation should map the chronology: when each development occurred, when its cost could reasonably be estimated, and when the costs were incurred [95], [97]. Unexplained increases between successive budgets merit challenge [92]. Where a phase was fully incurred before any application, Master Kaye’s provisional view in Persimmon was that those costs would be a matter for the costs judge in due course [25].
▶ Watch the case summary
CPR 3.15A | Costs Budget Revisions | Significant Developments And The Need To Act Promptly
Agreed Budget Variation Refused | Mutual Consent Intensifies, Not Reduces, Retrospective Scrutiny
CPR 3.15A | Costs Budget Revisions | Was The ‘Development’ Significant Enough?
Increase in value of claim not a significant development under s7.6 PD3E
Related service: costs management, including Precedent H budgets and CCMC representation.