The summary assessment of costs followed an application by Saudi Arabian Airlines Corporation (the claimant) for an extension of time to exchange disclosure certificates and extended disclosure lists. The original direction required disclosure in March 2025, which was subsequently extended by consent to 18 April 2025 as an interim measure whilst the parties negotiated a longer extension. When those negotiations failed to produce an agreed date, the claimant issued the present application.
The underlying dispute involved aviation-related proceedings in the Commercial Court, with Norton Rose Fulbright LLP acting for the claimant and Stephenson Harwood LLP representing the defendant, Sprite Aviation No.6 DAC. The claimant’s difficulties in meeting the disclosure deadline stemmed from Saudi Arabian data protection laws, though this was not initially disclosed in the application notice.
His Honour Judge Mark Pelling KC granted the extension to 8 August 2025 but did so subject to an undertaking from the claimant’s solicitors to inform the defendant’s solicitors within one working day if they became aware that the deadline would not or might not be met. The judge rejected the defendant’s request for an unless order and more draconian reporting obligations, finding that the undertaking struck the appropriate balance in addressing the delays.
Costs Issues Before the Court
The court was required to determine two principal costs issues. First, whether the defendant should recover its costs of and occasioned by the application, and if so, whether those costs should be assessed on the standard or indemnity basis. The defendant sought its costs on the grounds that the application was necessitated by the claimant’s failure to comply with the original disclosure timetable and its lack of transparency about the true reasons for the delay.
Second, the court undertook a summary assessment of the defendant’s costs, which totalled over £75,000. This required the judge to apply the well-established tests of reasonableness and proportionality to various categories of work claimed, including solicitors’ time, counsel’s fees, and disbursements. The assessment involved scrutinising hourly rates claimed significantly above the guideline rates, the number of fee earners involved, and the hours expended on various tasks.
The Parties’ Positions
The defendant submitted that it should recover its costs on the indemnity basis, arguing that the claimant had acted outside the norm expected in commercial litigation. The defendant relied on several factors: the claimant’s failure to comply with the original order, its failure to identify the real problem in the evidence initially filed in support, the ambiguous description of the disclosure exercise in Mr Springthorpe’s fourth witness statement, and the late filing of clarifying evidence in Mr Springthorpe’s fifth statement.
The claimant contended that costs should be in the case, characterising the application as relatively straightforward. Whilst accepting that a hearing was necessary due to the effect on the progress monitoring date, the claimant argued it was disproportionate for the defendant to resist the application as there was ample time in the timetable to accommodate the extension. The claimant emphasised that disclosure difficulties requiring extensions were not unusual in commercial litigation.
On summary assessment, the defendant sought to justify hourly rates of £744-760 for grade A fee earners (compared to guideline rates of £566), £432 for grade C (guideline £299), and £252 for grade D (guideline £205). The defendant argued these rates were justified given the aviation nature of the case and the requirement for specialist lawyers. The defendant also sought to recover fees for leading counsel’s involvement and extensive solicitor time across multiple fee earners.
The Court’s Decision
The judge ordered the defendant to recover its costs but on the standard basis, rejecting the application for indemnity costs. Applying the Excelsior test, the judge found that none of the factors relied upon, individually or collectively, justified an indemnity costs order. The judge observed that if every in-time application for an extension attracted indemnity costs, standard orders would be virtually unknown. Whilst the absence of information was aggravating and made it marginally more difficult for the defendant to respond, this did not warrant the exceptional remedy of indemnity costs.
On the principle of whether any costs order should be made, the judge found this to be finely balanced but ultimately concluded the application could have been avoided had the claimant either complied with the original order or sought an extension on a full and frank basis from the outset. The judge therefore awarded costs to the defendant on the standard basis.
In the summary assessment, the judge applied the principles from Kazakhstan Kagazy Plc v Zhunus, that proportionality in commercial litigation means the minimum sum required for a proper job to be done. Following Samsung Electronics Co. Ltd v LG Display Co. Ltd, the judge held that whilst guideline rates were the starting point, any excess must be clearly justified on reasonableness and proportionality grounds.
The judge found no coherent justification for departing from guideline rates, rejecting the argument that this being an aviation case warranted higher rates for what was essentially a straightforward disclosure extension application. With hesitation, the judge allowed London 1 rather than London 2 rates, primarily due to the size of the claim.
On specific items, the judge made significant reductions: attendances on clients were reduced from five to three hours for the grade C fee earner; the involvement of Mr Edward Cumming KC was disallowed entirely as neither reasonable nor proportionate for an extension application; attendance at the hearing was limited to one grade A fee earner rather than three solicitors; and travel time for attending counsel’s chambers remotely was disallowed. The judge allowed £8,000 for junior counsel’s brief fee despite reservations, acknowledging the additional work caused by the claimant’s late disclosure of material information.
For document preparation, the judge substantially reduced the claimed 40.6 hours across three fee earners for preparing for the CMC, allowing 2.5 hours for the grade A fee earner, 13.3 hours for the grade D fee earner, and three hours for the grade C fee earner. The costs lawyer’s fee was reduced from £1,625 to £1,200, finding the higher figure excessive for preparing a relatively simple costs schedule.
- CPR 52.18: Applications To Set Aside Permission Or To Impose Conditions Refused
- The Correct Approach To Summary Assessment | Guideline Hourly Rates Up By 35%?
- How Relevant Are The Guideline Hourly Rates?
- Indemnity Costs | Be Reasonable
- Non-Party Costs Order Application Denied Due to Significant and Unexplained Delay















