The High Court’s decision in The Winros Partnership v Global Energy Horizons Corporation [2025] EWHC 2044 (Ch) addresses when late-raised costs objections constitute a Henderson v Henderson abuse of process and the consequences of defective judicial case management in solicitor-client assessments.
Background
The case centres on three conditional fee agreements (CFAs) under which Rosenblatt Solicitors (now The Winros Partnership) acted for Global Energy Horizons Corporation in Chancery Division proceedings against a former associate, Mr Robert Gray, concerning alleged misappropriation of technology [§1]. The underlying dispute achieved mixed results: in December 2012, Vos J granted declarations that Mr Gray was in breach of fiduciary duty; in July 2015, Asplin J ordered Mr Gray to pay approximately £3.6 million; but Arnold J in May 2019 valued certain assets at nil and found no further sums payable [§2].
Three CFAs governed the retainer: CFA-1 (dated 8 December 2009), CFA-2 (dated 31 October 2010), and CFA-3 (dated 6 March 2013) [§§3–7]. Each contained provisions for an “Advance Fee” to be retained by Rosenblatt regardless of outcome, with additional fees and a success fee payable only on a “win”. CFA-3’s clause 14 set out termination provisions, including clause 14.3 which entitled Rosenblatt to end the agreement if it believed the client did not meet its responsibilities, in which case the client would pay fees for work done to the termination date and disbursements [§6(iv)].
The relationship between solicitor and client broke down, and Rosenblatt terminated the retainer by letter dated 24 February 2016. Trower J, on appeal from Master James, held that this termination was not pursuant to clause 14.3 but by Rosenblatt’s acceptance of Global Energy’s repudiatory breach [§9(v)].
Global Energy issued Part 8 proceedings on 1 April 2016 seeking detailed assessment [§25(i)]. This led to a 10-day preliminary issues hearing before Master James in 2019 [§15(i)], an appeal to Trower J determined in December 2021 [§§8–9], and ultimately an eight-day hearing including a five-day detailed assessment before Senior Costs Judge Gordon-Saker in 2024 [§10]. At that final hearing, Global Energy raised “Objection 1” for the first time, contending that the bills should be assessed at nil because when delivered, Global Energy was not liable to pay them as the fees remained contingent [§10]. The Senior Costs Judge upheld the objection, resulting in Rosenblatt’s costs being assessed at nil [§12].
Costs Issues Before the Court
The appeal concerned whether raising Objection 1 for the first time at detailed assessment—some eight years after proceedings commenced—constituted a Henderson v Henderson abuse of process. The court was required to determine:
- Whether Global Energy’s failure to raise Objection 1 at earlier hearings (including the 10-day preliminary issues trial before Master James) amounted to an abuse of process that should result in the objection being struck out [§§15–20].
- If abuse was established, whether there were exceptional circumstances excusing the late raising of the objection [§§24–27].
- The appropriate remedy if abuse was found [§§22–23].
The Senior Costs Judge had refused permission to appeal on the abuse of process ground; Joanna Smith J ordered that permission be considered at the appeal hearing [§13].
The Parties’ Positions
Rosenblatt’s Position: Rosenblatt argued that raising such a fundamental objection at this late stage was a clear Henderson v Henderson abuse [§11]. The Senior Costs Judge’s own findings supported this conclusion:
- He found that Objection 1 “could easily have been added” to Global Energy’s case at the preliminary issues hearing [§15(ii), Decision/[25]]
- He stated that “standard practice” in solicitor-client assessments is to determine liability issues first, before any detailed assessment [§15(v), Decision/[31]]
- He expressly found that Global Energy “should have pleaded what is now Objection 1 in the Particulars of Claim” [§15(iv), Decision/[28]]
Rosenblatt contended that where a party has had the opportunity to raise an issue and failed to do so, strike-out is the appropriate remedy, and that a costs order was an insufficient sanction [§§22–23].
Global Energy’s Position: Global Energy raised two points by respondent’s notice [§22]. First, it argued that even if there was an abuse, the Senior Costs Judge had applied an appropriate sanction in the form of a costs order and striking out should not follow automatically [§22]. Second, and primarily, Global Energy argued the Decision could be upheld on other grounds: namely, that Global Energy could not properly be criticised for raising Objection 1 late because the court’s own procedural directions had precluded earlier raising of the issue [§24].
The Court’s Decision
Mr Justice Marcus Smith granted permission to appeal, finding that on the facts stated in the Decision itself, he could see “no clearer case of a Henderson v Henderson type abuse of process” [§16]. The court was highly critical of the Senior Costs Judge’s reasoning, stating it was “so wrong as to be perverse” [§16].
The court identified fundamental errors in the Senior Costs Judge’s approach. The consideration of whether Objection 1 had been previously determined by Master James or Trower J missed the point entirely: “the point is not whether Objection 1 was previously determined (obviously it was not) but whether the opportunity to resolve it was wrongly forsaken (which, on the Decision’s findings, it clearly was)” [§20]. Similarly, asking whether the earlier decisions would have been different had Objection 1 been argued, or noting that those hearings would have taken place anyway, “misses the point” [§20]. Had Objection 1 been dealt with at those hearings, “later stages in these proceedings would have been unnecessary, and considerable cost and time would have been saved for all concerned” [§20].
The court rejected Global Energy’s argument that a costs order was an appropriate alternative to strike-out. Had the Senior Costs Judge properly found an abuse of process, “striking out would be – on the basis of the facts found in the Decision – the only appropriate course in this case” [§23].
However, the appeal ultimately failed because of facts not properly addressed in the Decision [§§24–27]. Examination of the procedural history revealed that by an order dated 16 June 2016, Master James had acted of her own motion to direct only two preliminary issues, without first requiring the parties to plead their cases on liability [§25(iii)]. Marcus Smith J found this to be “a major procedural error on the part of the court” [§25(iv)]:
- The court disregarded Rosenblatt’s suggestion of dealing with all questions of “liability” first [§25(iv)(a)]
- The court directed only two preliminary issues, apparently considering these were the only possible liability issues—but Objection 1 was not identified [§25(iv)(b)]
- The court should have required pleadings first, then made case management directions in light of the issues taken; instead, “case management preceded pleadings, with the result that the true issues between the parties were never identified until it was too late” [§25(iv)(c)–(d)]
In these circumstances, Global Energy and Rosenblatt “were quite properly following the direction of the court” [§26]. It would have been improper for Global Energy to shoehorn additional issues into an expressly limited preliminary issues hearing. There was therefore “nothing in Global Energy’s conduct to criticise, and it would be unfair to prevent Global Energy from taking Objection 1 now” [§26].
For these reasons—which were “not the reasons of the Senior Costs Judge”—permission to appeal was granted, but the appeal was dismissed [§28].















