The Court of Appeal’s decision in R (Nisar and Others) v SSHD; R (Mammedov) v SSHD [2025] EWCA Civ 1646 confirms that the precise language of Home Office deadline commitments determines whether a legal obligation is created, with direct consequences for costs recovery in settled immigration judicial reviews.
Background
The appeals concerned two separate judicial review claims against the Secretary of State for the Home Department (SSHD), which were heard together. In both, the appellants were foreign nationals living outside the UK whose applications for entry clearance as visitors had been refused. Following pre-action correspondence, the SSHD in each case agreed to withdraw the challenged decision and make a new one, indicating a timeframe for doing so. The fresh decisions were made shortly after the indicated dates and were again refusals. In the interim period between the deadline passing and receiving the decision, each appellant commenced a claim for judicial review challenging the delay. These claims were discontinued by consent once the decisions were received. The sole remaining dispute was over costs [§1–5].
In the case of Nisar, the appellants (a mother and her four children, all Pakistani nationals) had a protracted history of refusals and reconsiderations [§6–8]. In a letter dated 25 July 2023, the SSHD stated that “a decision regarding your client’s UK visitor visa will be made by the 21/08/2023, absent special circumstances” [§11]. The decision to refuse was made on 22 August but not served until 23/24 August 2023 [§12–13]. The judicial review claim had been lodged on 22 August 2023, the same day the decision was made but before it was communicated [§12, §16]. The parties agreed to discontinue the claim, leaving costs to be determined. Upper Tribunal Judge Sheridan made no order as to costs, finding both parties’ conduct contributed to the unnecessary proceedings [§16].
In the case of Mammedov, the appellant was a national of Turkmenistan who had been living in Turkey as a student since 2016 [§19]. The SSHD’s letter of 20 December 2024 stated that “Barring complexities, the SSHD aims to issue a reconsidered decision on your client’s visit visa application within 3 months of the date of this response to your letter before claim (by 20 March 2025, absent special circumstances)” [§20]. A reminder email was sent on Sunday 16 March 2025, warning that proceedings would be issued if no decision was made by the deadline [§22]. No decision was made by 20 March, and proceedings were issued on 21 March 2025 [§23]. A refusal decision was made on 28 March 2025 [§24]. The claim was discontinued by consent. Upper Tribunal Judge Hirst also made no order as to costs, citing the appellant’s failure to comply with the Pre-Action Protocol regarding the new issue of delay [§27].
Costs Issues Before the Court
The central costs issue in both appeals was whether the Upper Tribunal judges had erred in their discretion by making no order as to costs, rather than awarding costs to the appellants as the successful parties. The legal context was the settlement of judicial review proceedings before a substantive hearing, where the defendant public authority provides the substantive remedy (a decision) after proceedings are issued. The court was required to apply the principles from R (M) v Croydon LBC [2012] EWCA Civ 595 and related authorities to determine if the appellants could be considered “successful” and whether there was a sufficient causal link between the issued claim and the obtaining of the decision to justify a costs order in their favour [§30–36].
The Parties’ Positions
The appellants argued they were the successful parties as they obtained the remedy sought—a decision on their application—as a result of issuing proceedings. In Nisar, it was submitted that the SSHD’s unequivocal commitment to decide by a specific date created a legal obligation, the breach of which reasonably triggered litigation [§17]. The judge’s conclusion that the appellants should have chased for a decision was irrational. In Mammedov, the appellant argued the reminder email of 16 March was sufficient compliance with the Pre-Action Protocol, and a further formal letter was not required given the SSHD’s prior commitment and failure to act [§28].
The respondent SSHD opposed the appeals. It argued that in neither case were the appellants “successful” in a relevant sense, as the eventual decisions were refusals. It contended there was no, or insufficient, causal link between the issued claims and the decisions being made. In Mammedov, the SSHD supported the judge’s finding that a fresh Pre-Action Protocol letter was required to complain about the delay, a new issue not raised in the earlier correspondence.
The Court’s Decision
The Court of Appeal allowed the appeal in Nisar but dismissed the appeal in Mammedov. Applying the principles from R (M) v Croydon, the court held that the exercise of discretion on costs could be interfered with only if the judge erred in principle, considered irrelevant matters, or the decision was wholly wrong [§30].
In Nisar, the court found the claim fell squarely within category (i) of M v Croydon (where a claimant is wholly successful) [§48]. The SSHD’s letter of 25 July 2023 was sufficiently clear to amount to a legal obligation to decide by 21 August 2023, even if it was not an “enforceable undertaking” in the sense of being subject to specific performance or committal [§46]. The breach of that obligation, without citing special circumstances, made the issuance of proceedings reasonable. The court rejected the Upper Tribunal’s view that the appellants should have contacted the SSHD first, noting the unequivocal nature of the commitment [§46]. The claim was causative of the relief because, without the threat of litigation backed by the deadline, the delay would have been greater [§47]. The SSHD was therefore ordered to pay the appellants’ costs of the brief period up to the compromise [§48].
In Mammedov, the court found no error in the judge’s exercise of discretion [§49–50]. The SSHD’s letter used the language “aims to issue,” which did not create a legal obligation akin to the promise in Nisar [§49]. The issue of delay had not been raised in prior pre-action correspondence, and the delay had not reached the stage where it was so excessive as to be manifestly unreasonable [§49]. The Upper Tribunal was entitled to conclude that raising this new issue via a proper Pre-Action Protocol letter before issuing proceedings was reasonable and in accordance with the overriding objective. The failure to do so constituted a good reason to depart from the general costs rule [§49].
The court emphasised that Patten LJ’s statement in Speciality Produce Ltd v Secretary of State for the Environment [2014] EWCA Civ 225—that the claim “must be causative of the relief obtained”—was not to be treated as a statute nor as imposing a strict causation test in every case [§47]. The different outcomes in the two appeals turned on their distinct factual matrices, particularly the nature of the SSHD’s commitment and the reasonableness of commencing proceedings without further pre-action steps.

Costs In Withdrawn Judicial Review Claims
CPR 44.2 And The Courts’ Discretion As To Costs
CPR 38.6: Discontinuance And Costs – The Legal Principles
Summary Determination Of Costs Without A Trial
Who Should Pay The Costs Of A Withdrawn And Undetermined Application?
No Order As To Costs Despite Successful Application | Novelty And Conduct Considered







![BARONESS LAWRENCE & ORS v ASSOCIATED NEWSPAPERS LIMITED [2025] EWHC 3207 (KB)](https://tmclegal.co.uk/wp-content/uploads/2025/12/MATRIX-copy-300x169.jpg)







