Court Deprecates Paying Party's Opportunistic Conduct In Detailed Assessment Proceedings

Paying parties who opportunistically exploit minor procedural breaches, rather than cooperating to resolve them, risk adverse costs consequences and judicial criticism under the principles established in Denton.

The Parties' Positions on Relief From Sanctions and Opportunistic Conduct
In Long v Value Properties Ltd & Ocean Trade Ltd , Mr Justice Barling allowed the claimant’s appeal from the decision of Costs Judge Master Rowley concerning a breach during detailed assessment. The underlying dispute over parking spaces was settled, with costs to be assessed. The claimant commenced assessment within time by serving a notice and bill under CPR r.47.6 but omitted further information required by Practice Direction 47PD.32.5(1)(c) and (d) and 47PD.32.7, namely the CFA and a statement of reasons for the success fee. The defendants raised this in points of dispute; the claimant served the documents late and applied for relief. Master Rowley found a breach, applied the sanction in CPR r.44.3B(1)(d) to disallow the entire success fee, and refused relief. On appeal, Barling J held the breach was established, as the Practice Direction implied the information must be served at commencement to ensure a fair process under the overriding objective, following Middleton v Vosper Thorneycroft (UK) Ltd. However, he found the applicable sanction was under CPR r.44.3B(1)(c) of the Civil Procedure Rules 1998, which imposes a graduated disallowance for the period of default, not the ‘all or nothing’ penalty under sub-paragraph (d). Alternatively, applying the Denton v TH White Ltd guidance to CPR r.3.9, he held the breach was neither serious nor significant, was remedied promptly, and caused minimal prejudice, while the defendants’ conduct was opportunistic. Relief would have been granted in full. The appeal was allowed, reversing the costs order below.

...the defendants preferred to take advantage of the claimant's oversight by choosing not to inform the claimant earlier, and going ahead with service of points of dispute ... which they knew would require amendment once the Further Information was received. Thereafter they declined to cooperate with the claimant, and were unwilling to amend the points of dispute and avoid the need for an application for relief. It is clear, as the Judge found, that there was no significant prejudice to the defendants, or to the efficient conduct of the assessment proceedings at proportionate cost, or to the court or to other litigants as a result of the breach itself. It is evident that in so far as there has been unnecessary cost, delay and use of the court's finite resources in hearing the application for relief from sanctions and this appeal, this is the result of what in my view was the unreasonable, opportunistic and non-cooperative approach of the defendants to the claimant's unfortunate oversight.

Citations

Denton v TH White Ltd & Others [2014] EWCA Civ 906 Relief from sanctions under CPR 3.9 required a three-stage approach: assess the seriousness and significance of the breach; consider why the default occurred; and evaluate all the circumstances of the case to deal justly with the application, giving particular weight to the need for litigation to be conducted efficiently and at proportionate cost, and to enforce compliance with rules. Mitchell v News Group Newspapers Ltd [2013] EWCA Civ 1537; [2014] 1 WLR 795 Where there is a serious or significant breach without good reason, relief from sanctions will usually be refused, with the court giving particular weight to the need for compliance with rules and the efficient conduct of litigation. Middleton v Vosper Thorneycroft (UK) Ltd (Winchester County Court, 2 June 2009) The documents required under paragraph 32.7 of the Costs Practice Direction must be served at the commencement of the detailed assessment proceedings to ensure procedural fairness and efficiency. Light On Line Ltd and Another v Zumtobel Lighting Ltd [2013] 1 Costs LR 129 A failure to serve the insurance certificate, as required under paragraph 32.5 of the Costs Practice Direction, at the same time as the bill of costs constituted a breach justifying disallowance of the premium unless relief from sanctions was granted. Jones v MBNA International Bank Ltd (Court of Appeal, 30 June 2000, unreported) Litigants cannot raise on appeal issues that could have been but were not raised before the lower court, unless the case is exceptional and justice so requires. Slack & Partners Ltd v Slack [2010] EWCA Civ 204 Appellants generally cannot reopen arguments on appeal that should have been advanced at first instance, reflecting the principle of finality in litigation.

Key Points

  • Where a conditional fee agreement (CFA) includes a success fee, the receiving party is required to serve the Further Information (comprising the reasons for the percentage increase or risk assessment and a copy of the CFA) at the commencement of detailed assessment proceedings. This obligation arises by necessary implication from the combined effect of CPR r.47.6(1), r.47.9, and Practice Direction 47PD.32.5 and 32.7, to ensure procedural coherence and fairness.
  • A failure to serve the required Further Information about a CFA success fee at the commencement of detailed assessment proceedings constitutes a breach of the CPR. However, the detailed assessment proceedings are validly commenced by service of the notice of commencement and the bill of costs alone, as specified in CPR r.47.6(1).
  • The sanction for delayed provision of Further Information about a CFA success fee is governed by CPR r.44.3B(1)(c), which imposes a proportionate disallowance for the period of non-compliance. In contrast, CPR r.44.3B(1)(d) applies only where there has been a complete failure to provide the specified information during the assessment proceedings.
  • When determining whether to grant relief from sanctions under CPR r.3.9, the court must assess: (i) the seriousness and significance of the breach, (ii) the reason for the default, and (iii) all the circumstances of the case, including the need for litigation to be conducted efficiently and at proportionate cost and the need to enforce compliance with rules, practice directions and orders. A breach that is promptly rectified and causes no material prejudice may be considered neither serious nor significant.
  • A party’s unreasonable and opportunistic conduct in opposing relief from sanctions—such as failing to cooperate in resolving minor procedural errors and seeking to take advantage of an oversight—is a relevant circumstance under CPR r.3.9 and may weigh in favour of granting relief.

"In my view when looked at in its context as discussed above, the breach here is properly regarded as 'insignificant' and therefore 'trivial' as those expressions are understood in the light of the guidance in Mitchell (see in particular paragraph 40 of the judgment of the Court of Appeal in that case). For the same reasons I consider the breach to be neither serious nor significant in the terms of the Denton guidance."

Key Findings In The Case

  • The Claimant’s solicitors commenced detailed assessment proceedings by serving the required documents (notice of commencement and bill of costs) on 17 October 2013, but inadvertently failed to serve the Further Information required under CPR Practice Direction 47PD.32.7 at the same time, constituting a breach of the disclosure obligation in relation to additional liabilities, namely the success fees under a CFA.
  • The Further Information—comprising a copy of the CFA and the risk assessment or reasons for the percentage uplift—was served on the Defendants on 22 November 2013, approximately five weeks after commencement of the assessment proceedings; the breach was promptly rectified once discovered, and the application for relief from sanctions was made very shortly thereafter.
  • The failure to serve the Further Information did not prevent proper commencement of detailed assessment proceedings under CPR r.47.6(1), which only requires service of the bill of costs and notice of commencement; thus, the Claimant was still within the permitted three-month timeframe under CPR r.47.7 when proceedings were initiated.
  • The applicable sanction under CPR r.44.3B for a delayed disclosure of Further Information relating to an additional liability (such as a success fee) was held to be under r.44.3B(1)(c), which provides for a disallowance limited to the period of default, rather than under r.44.3B(1)(d), which applies to a total failure to disclose during assessment proceedings and carries an “all or nothing” consequence.
  • The Judge found that the breach was neither serious nor significant and caused no material prejudice or disruption to the efficient conduct of the assessment; the Defendants’ refusal to cooperate or resolve the matter informally was deemed unreasonable and opportunistic, and this context justified full relief from sanctions under CPR r.3.9.

"I would also add that the defendants' behaviour here has been precisely the kind of opportunistic, and non-cooperative conduct in litigation condemned by the Court of Appeal in Denton. Had the defendants taken a different course the matter could probably have been completely resolved within the overall period of the extension of time which they applied for and were granted by the claimant, or very soon thereafter. This would have saved the parties and the court the time and expense of a lengthy hearing before the Judge and an even longer appeal hearing before me."

The decision in Long v Value Properties Ltd & Anor [2014] EWHC 2981 (Ch) establishes that a short delay in serving additional liability information during detailed assessment proceedings constitutes neither a serious nor significant breach. Paying parties who exploit such oversights rather than cooperating to remedy them engage in opportunistic conduct that detailed assessment and CPR 3.9 applications appropriately condemn, as established in Denton v TH White Ltd

Background

The dispute originated in approximately 2011 concerning the use of parking spaces adjoining property where the claimant, Norah Christina Long, and her late husband were lessees. The claimant’s solicitors informed the defendants, Value Properties Limited and Ocean Trade Limited, that the claimant was represented under a conditional fee agreement dated 12 October 2011 with a success fee [§2]. A notice of funding (N251) was served on the defendants in accordance with the Civil Procedure Rules [§2]. Proceedings were issued on 7 February 2013 [§3]. Following the death of the claimant’s husband, the claim continued in her name alone [§3]. The matter was settled by a consent order made on 15 August 2013, which required the defendants to pay the claimant’s costs, to be subject to detailed assessment on a standard basis if not agreed [§3].

The success fees of counsel and solicitors together totaled £48,462, forming part of a total bill of £131,937 [§8].

Detailed assessment proceedings were commenced on 17 October 2013 when the claimant’s solicitors served the notice of commencement (Form N252) and the bill of costs, as required by CPR r.47.6(1) [§4]. However, the claimant’s solicitors failed to serve the Further Information, comprising a statement of reasons for the percentage increase or a copy of the risk assessment, and a copy of the conditional fee agreement itself, as mandated by Practice Direction 47PD.32.5(1)(c) and (d) and 47PD.32.7 [§5].

On 5 November 2013, the second defendant requested a 14-day extension to serve points of dispute, and on 6 November the claimant agreed to extend time for both defendants [§6]. Points of dispute were filed on 14 November 2013 [§6]. These points of dispute raised, for the first time, the claimant’s non-compliance with 47PD.32 [§6-7]. The claimant served the Further Information on 22 November 2013 [§7] and issued an application for relief from sanctions on 28 November 2013 [§7].

The application was heard by Costs Judge Master Rowley on 13 January 2014. Master Rowley expressed “qualms” about the ease with which a breach of this requirement could occur compared with the draconian nature of the sanction, and noted the difference between this situation and the less severe sanctions for failure to serve notice of funding (N251) [§14]. Nevertheless, he found a breach of the CPR, applied the sanction under CPR r.44.3B(1)(d), and refused relief [§9]. Permission to appeal was granted [§9].

Costs Issues Before the Court | Opportunistic Conduct and CPR 3.9

The appeal raised three principal costs issues [§16]. First, whether the claimant had breached the CPR by failing to serve the Further Information at the commencement of the detailed assessment proceedings. Second, if a breach had occurred, what was the applicable sanction under the CPR, particularly whether it fell under CPR r.44.3B(1)(c) or (d). Third, if the more severe sanction under r.44.3B(1)(d) applied, whether relief from that sanction should be granted pursuant to CPR r.3.9.

Significantly, the appeal was heard before the Court of Appeal’s decision in Denton v WH White Ltd [§1], but both parties subsequently provided written submissions on the effect of that judgment in the context of the appeal [§1, §56].

The Parties’ Positions on Relief From Sanctions and Opportunistic Conduct

The claimant argued that there was no breach of the CPR because the rules did not explicitly require the Further Information to be served at the commencement of detailed assessment proceedings; it could be served at any time during the proceedings [§36]. In the alternative, if a breach was found, the applicable sanction was under CPR r.44.3B(1)(c), which imposed a graduated disallowance for the period of default, rather than the “all or nothing” sanction under r.44.3B(1)(d) [§42-44]. The claimant further submitted that, even if r.44.3B(1)(d) applied, the breach was trivial or, in all circumstances, relief should be granted under CPR r.3.9 [§55]. The claimant relied on the lack of prejudice to the defendants, the prompt rectification of the omission, and the defendants’ opportunistic conduct in not notifying the claimant of the oversight earlier [§7, §68-70].

The defendants contended that the Further Information was required to be served at the commencement of detailed assessment proceedings by necessary implication from the structure of the CPR and Practice Direction [§26-31]. They argued that the applicable sanction was under CPR r.44.3B(1)(d), as the breach related to a failure to disclose reasons for the percentage increase [§42]. The defendants submitted that the breach was serious and significant, caused by an oversight which was not a good reason, and that relief should be refused to enforce compliance with rules and practice directions [§67]. They emphasised the tight timetable for points of dispute and the prejudice caused by having to amend them [§67].

The Court’s Decision

The court held that there was a breach of the CPR [§37-40]. It found that the obligation to serve the Further Information at the commencement of detailed assessment proceedings was implied from the interaction of CPR r.47.6, r.47.9, and Practice Direction 47PD.32 [§37-39]. This interpretation was necessary to ensure the efficiency and fairness of the assessment process, aligning with the overriding objective under CPR r.1.2 [§40]. The court referenced Middleton v Vosper Thorneycroft (UK) Ltd [§30-31] and Light On Line Ltd v Zumtobel Lighting Ltd [§32-33] in support of this conclusion.

On the applicable sanction, the court determined that CPR r.44.3B(1)(c) applied, not r.44.3B(1)(d) [§54]. The wording of r.44.3B(1)(c) addressed failures to provide information “by the time required”, imposing a graduated sanction for the period of default, whereas r.44.3B(1)(d) was intended for complete failures to disclose [§42-54]. This interpretation avoided anomalies and better served the overriding objective, particularly given the disproportionate nature of the sanction under r.44.3B(1)(d) for minor delays [§53-54].

In the alternative, if r.44.3B(1)(d) applied, the court found that relief from sanctions should be granted under CPR r.3.9 [§55-74]. Applying the three-stage Denton guidance [§57-66], the breach was neither serious nor significant [§71]. The delay of approximately three weeks was short [§67], rectified promptly once brought to the claimant’s attention [§13, §68], and caused no substantial prejudice [§13, §70].

Critically, the defendants had contributed to the length of the default by seeking an extension for service of points of dispute without notifying the claimant of the omission [§68]. The court found it unclear whether the defendants knew of the breach when the second defendant sought the extension on 5 November 2013, though they were certainly aware by 14 November when they served points of dispute [§68]. Had the defendants wished to shorten the length of default and save costs, they could have informed the claimant before preparing points of dispute and sought an extension to take stock of the Further Information when supplied – the claimant would have agreed to such a request [§68].

Instead, the defendants “preferred to take advantage of the claimant’s oversight by choosing not to inform the claimant earlier, and going ahead with service of points of dispute (after obtaining an extension of time for that purpose) which they knew would require amendment once the Further Information was received” [§69]. Thereafter they declined to cooperate with the claimant and were unwilling to amend the points of dispute to avoid the need for an application for relief [§69].

The court concluded that “in so far as there has been unnecessary cost, delay and use of the court’s finite resources in hearing the application for relief from sanctions and this appeal, this is the result of what in my view was the unreasonable, opportunistic and non-cooperative approach of the defendants to the claimant’s unfortunate oversight” [§70].

The judge found that when looked at in its context, “the breach here is properly regarded as ‘insignificant’ and therefore ‘trivial’ as those expressions are understood in the light of the guidance in Mitchell… For the same reasons I consider the breach to be neither serious nor significant in the terms of the Denton guidance” [§71]. The judge noted that Master Rowley “appears to have fallen into the error by attaching insufficient weight to the circumstances surrounding the breach as well as to the absence of any significant prejudice of any kind to anyone” [§71].

Master Rowley had also fallen into the error identified by the Majority in Denton, in that having concluded the breach was not trivial and that there was no good reason for it, he regarded the application for relief from sanctions as bound to fail, without going on to consider whether that was the appropriate outcome in “all the circumstances of the case” as required by r.3.9 [§72].

Considering all circumstances, including the nature and effect of the breach, the defendants’ conduct, the speed with which the claimant remedied the default and applied for relief, and the need to enforce compliance with rules, practice directions and orders, the just disposal of the application required complete relief from the sanction to be granted [§73].

The court added that “the defendants’ behaviour here has been precisely the kind of opportunistic, and non-cooperative conduct in litigation condemned by the Court of Appeal in Denton” [§76]. Had the defendants taken a different course, “the matter could probably have been completely resolved within the overall period of the extension of time which they applied for and were granted by the claimant, or very soon thereafter. This would have saved the parties and the court the time and expense of a lengthy hearing before the Judge and an even longer appeal hearing” [§76].

The appeal was allowed on both grounds [§75].

Setting Aside Default Costs Certificate – Denton Criteria Applied

Directly discusses Denton three-stage test for CPR 3.9 applications in detailed assessment context

Defendants Fail To Have US$3.7m Default Costs Certificate Set Aside

Application of Denton guidance to detailed assessment procedural breaches with CPR 47.12 analysis

CPR 3.14 | Late Costs Budget | Relief From Sanctions Denied

CPR 3.9 sanctions where court found persistent failure to engage – contrasts with relief granted for minor oversight

No Excuses: Relief From Sanctions Refused Following Late Filing

High Court applies CPR 3.9 refusing relief where breach serious and significant with no good reason

CPR 52.18: Applications To Set Aside Permission – Mitchell and Denton Principles

Court of Appeal confirms Mitchell strict approach – discusses sanctions regime that Denton sought to moderate

Retrospective CFAs and Success Fees in Detailed Assessment

Additional liability disclosure requirements and reasonableness of success fees

Specialist costs services across the UK

TMC Legal provides expert costs drafting, negotiaton and costs budgeting services together with representation in detailed assessment hearings. Our experienced costs lawyers and law costs draftsmen act nationwide. Contact us today.

Keywords

LONG V VALUE PROPERTIES LTD & OCEAN TRADE LTD [2014] EWHC 2981 (CH) | THE HONOURABLE MR JUSTICE BARLING | CPR 3.9 | CPR 44.3B(1)(C) | CPR 44.3B(1)(D) | CPR 47.6 | CPR 47.7 | CPR 47.9 | 47PD.32.5(1)(C) | 47PD.32.5(1)(D) | 47PD.32.7 | CONDITIONAL FEE AGREEMENT | ADDITIONAL LIABILITY | SUCCESS FEE | RELIEF FROM SANCTIONS | DENTON V TH WHITE LTD [2014] EWCA CIV 906 | MITCHELL V NEWS GROUP NEWSPAPERS LTD [2013] EWCA CIV 1537 | POINTS OF DISPUTE | NOTICE OF COMMENCEMENT | N252 | N251 | FAILURE TO DISCLOSE FUNDING INFORMATION | LATE SERVICE OF FURTHER INFORMATION | COSTS PRACTICE DIRECTION | PROPORTIONALITY OF SANCTION | DISCRETION UNDER CPR 3.9 | TRIVIALITY TEST | SERIOUS OR SIGNIFICANT BREACH | OVERRIDING OBJECTIVE | OPPORTUNISTIC CONDUCT | NON-COOPERATION IN LITIGATION | MASTER ROWLEY | MIDDLETON V VOSPER THORNEYCROFT (UK) LTD | LIGHT ON LINE LTD V ZUMTOBEL LIGHTING LTD [2013] 1 COSTS LR 129 | APPEAL FROM SENIOR COURT COSTS OFFICE | DETAILED ASSESSMENT PROCESS | RISK ASSESSMENT DISCLOSURE | COSTS SANCTIONS | DENTON THREE-STAGE TEST | OVERSIGHT AS BREACH | COSTS JURISPRUDENCE
© 2025 TMC Legal Limited - Costs Lawyers, Draftsmen & Consultants. All Rights Reserved.
Company Number: 12348782 | Registered Office: 46-48 The Green, Wooburn Green, HP10 0EU