Background
The case concerned an application by Volga-Dnper Logistics B.V. (the Defendant) to vary an interim payment order made by Bryan J on 11 February 2025. The order required the Defendant to make payments totalling USD 202,811,264 to Celestial Aviation Trading entities (the Claimants) by 25 February 2025, plus a £50,000 payment on account of costs. The Defendant sought to vary the order so that its payment obligations would only commence after obtaining licences from OFSI (UK) and OFAC (US) sanctions authorities.
The dispute arose from aircraft lease agreements between the Claimants and two Russian airlines, with the Defendant providing guarantees. Following Russia’s invasion of Ukraine in February 2022 and subsequent sanctions, the Claimants terminated the leases and demanded payment from the Defendant under the guarantees. When payment was not forthcoming, proceedings were issued in May 2022.
The procedural history included delays due to the Defendant’s difficulties in securing legal representation under sanctions regimes. The Defendant’s ultimate beneficial owner, Alexey Isaykin, was designated under UK sanctions in June 2022 and US sanctions in August 2024. After various adjournments, Bryan J heard the Claimants’ interim payment application on 11 February 2025, making the order now sought to be varied.
Costs Issues Before the Court
The key costs-related issue was whether the court should vary the interim payment order to make payment conditional upon the Defendant obtaining sanctions licences. The Defendant argued that without such variation, it faced an impossible choice between complying with the order (potentially breaching sanctions) or being in contempt of court for non-payment.
The court had to consider: (1) the principles governing variation of interim payment orders under CPR 25.20(6)(b); (2) the impact of UK and US sanctions legislation on the Defendant’s ability to comply; and (3) whether the circumstances justified varying the original order.
The Parties’ Positions
The Defendant submitted that variation was necessary because:
- Complying with the order without licences would breach UK and US sanctions
- The original order was made without full consideration of sanctions implications
- It had promptly applied for necessary licences (though only after the payment deadline)
- It faced potential contempt proceedings despite being unable to comply lawfully
The Claimants opposed variation, arguing:
- The court was aware of sanctions issues when making the original order
- No material change of circumstances or misstatement justified variation
- The order itself did not breach sanctions – compliance was the Defendant’s responsibility
- Variation would prejudice their ability to enforce against the Dutch-held funds
- They would not pursue contempt proceedings while sanctions prevented compliance
The Court’s Decision
The court refused to vary the interim payment order, finding:
- Variation principles: Following Tibbles v SIG, variation requires a material change of circumstances or misstatement. Neither was established here as the court was aware of sanctions issues when making the original order.
- Sanctions impact: While sanctions created practical difficulties for the Defendant:
- The order itself did not breach sanctions (following Mints and R v R)
- UK sanctions were unlikely to be breached as the Defendant was Dutch and funds would go to Ireland
- US sanctions concerns were mitigated as ING would not release funds without OFAC approval
- The Serious Crime Act 2007 offence risk was not made out
- Practical considerations:
- Variation would weaken the Claimants’ position in Dutch enforcement proceedings
- The Defendant delayed both its variation application and licence requests
- The Claimants’ assurance against contempt proceedings addressed the Defendant’s key concern
The court emphasised that while sanctions created compliance difficulties, this did not automatically justify varying the order. The original order remained appropriate as it did not itself breach sanctions and preserved the Claimants’ enforcement position.















