The case concerned a claim by Xtellus Capital Partners Inc against DL Invest Group PM S.A. for a success fee payable under a mandate agreement. The Claimant had provided services to the Defendant in relation to the arrangement of two financing facilities. The first facility was dated 20 September 2022, and the second was an amendment and restatement agreement dated 23 May 2023. The success fee was calculated at 1.25% of the total amount of financing, amounting to €1,542,500 for the first facility and €249,743.93 for the second. The claim was issued on 13 February 2023. Following a trial, judgment was entered in favour of the Claimant on 28 July 2025 for the full sum of €1,792,247.93, to be paid by 11 August 2025. This judgment deals with the consequential matters of interest and costs.
Costs Issues Before the Court
The court was required to determine several consequential issues arising from the substantive judgment. These included: the applicable dates from which pre-judgment interest should run; the correct rate of pre-judgment interest; whether currency fluctuations affected the interest calculation; the appropriate rate of post-judgment interest; the basis on which the Claimant’s costs should be assessed (standard or indemnity); whether the Claimant’s costs budget should be varied; the rate of interest to be applied to costs; and the amount of a payment on account of costs.
The Parties’ Positions
On the issue of when the judgment sum fell due, the Claimant submitted that the full sum was due on 20 September 2022, pursuant to clause 4 of the mandate. The Defendant argued that the sums fell due in tranches based on drawdown dates, or alternatively, that the first sum fell due on 3 October 2022 (the date of an invoice) and the second on 23 May 2023.
Regarding the pre-judgment interest rate, both parties agreed that the Euro Interbank Offered Rate (Euribor) plus 1% should apply, as the judgment was in Euros. The Defendant submitted that the forward-looking 12-month rate of 2.05% (plus 1%) at the judgment date should be used. The Claimant argued for a weighted average of the 12-month Euribor rates between September 2022 and July 2025, which equated to 3.24% (plus 1%). The Defendant also submitted that no pre-judgment interest should be awarded due to a currency fluctuation windfall enjoyed by the Claimant.
For post-judgment interest, the Claimant, citing Britned v ABB, sought a rate of 8%, akin to the Judgments Act rate for sterling. The Defendant contended for a rate based on the forward-looking Euribor.
On the basis of assessment, the Claimant sought an order for indemnity costs. It argued the Defendant’s conduct took the case out of the norm, citing a dishonest defence supported by dishonest evidence, including findings that its evidence was “fanciful”, “patently false”, and “bordered on the outrageous”. The Defendant contended that the case was merely hard-fought commercial litigation with no procedural failings, and an indemnity basis order was not justified.
The Claimant also applied to vary its costs budget upwards by £104,876.54. The Defendant opposed this application.
On interest on costs, the Claimant sought a rate of US Prime plus 1%, reflecting its US Dollar operations. The Defendant’s position on this point was not detailed in the judgment.
Finally, for the payment on account, the Claimant sought 90% of its total budgeted and variation costs (£714,562.70), plus interest. The Defendant’s position was not explicitly stated.
The Court’s Decision
The court held that the success fee for the first facility fell due on 3 October 2022 (the invoice date) and the fee for the second facility fell due on 23 May 2023. This represented a waiver of the Claimant’s strict contractual rights concerning the first payment.
On pre-judgment interest, the court applied the compensatory principle and adopted a broad-brush approach. It awarded interest at a rate of 4.24% (a weighted average Euribor of 3.24% plus 1%) from the respective due dates. The court rejected the Defendant’s argument on currency fluctuation, finding it impermissible to investigate what the Claimant would have done with the money. The court upheld the standard approach of compensating a claimant for being kept out of the judgment currency.
For post-judgment interest, the court again applied the compensatory principle. It found the Claimant’s proposed 8% rate would overcompensate them, as it was based on a US Dollar borrowing cost, not the Euro judgment currency. The court awarded a forward-looking rate of 3.05% (a Euribor rate of 2.05% plus 1%).
The court found this was a clear case for ordering costs to be assessed on the indemnity basis. It concluded the Defendant’s conduct was well outside the ordinary and reasonable conduct of proceedings, taking the case out of the norm. This was based on findings that its defence was “thin”, “far-fetched”, and “fanciful”, and that its evidence was “patently false” and “bordered on the outrageous”. The court held that this widespread conduct justified a full indemnity costs order, not one limited to specific phases.
The court declined to rule on the Claimant’s application to vary its costs budget. It reasoned that as costs were to be assessed on the indemnity basis, CPR 3.18 (which requires a “good reason” to depart from a budget) did not apply. The assessing court could therefore depart from the budget more freely, making a variation order unnecessary and potentially hollow.
On interest on costs, the court awarded interest at the Bank of England base rate plus 1 percentage point, not the US Prime rate sought by the Claimant. It held that by choosing an English jurisdiction clause, the Claimant must be taken to have accepted that costs would be incurred in sterling.
Finally, the court ordered a payment on account of costs of £700,000, plus £36,750 in interest (representing 5.25% per annum for one year). This was a round figure based on the Claimant’s budgeted costs and the court’s wide discretion.
Indemnity Basis Costs Following Discontinuance – Examines factors that lead to indemnity basis costs, including speculative pursuit of weak claims and allegations of commercial impropriety
Speculative Claims, Indemnity Costs And The Effect Of An Approved Costs Budget – Discusses when conduct justifies indemnity costs and the “out of the norm” test from Excelsior
CPR 3.18(b) | Underspend Does Not Constitute Good Reason To Depart From An Approved Budget – Directly relevant to the budget variation issue and CPR 3.18 application
CPR 44.2(8) | Payments On Account In Costs Budgeted Cases – Covers payment on account principles and the approach to budgeted costs in setting amounts
Indemnity Costs Awarded For Unsubstantiated Fraud Allegations In Original Pleading – Recent 2025 case on indemnity costs for dishonest pleadings and conduct outside the norm