The Technology and Construction Court’s decision in The New Lottery Company Limited and Northern & Shell Plc v The Gambling Commission [2026] EWHC 1311 (TCC) addresses when cumulative unreasonable conduct from the outset of proceedings justifies indemnity costs across all claims, and whether proportionality is relevant to that assessment.

Background

This matter arose from proceedings brought in the Technology and Construction Court by The New Lottery Company Limited and Northern & Shell Plc (together, the claimants) against the Gambling Commission (the defendant), with Allwyn Entertainment Ltd, Allwyn International AG, and Camelot UK Lotteries Limited joined as interested parties. The proceedings concerned two distinct but intertwined claims: the Process Claim and the Modifications Claim, both arising from the fourth National Lottery competition, which the claimants described as “the most financially significant procurement process in UK history”.

The Process Claim challenged the conduct of the competition itself, including the evaluation and award process. The Modifications Claim concerned modifications made to the enabling agreement following the award decision. The claimants sought damages in excess of £1 billion and a declaration of ineffectiveness, which, if granted, would potentially have brought the National Lottery to a standstill. The proceedings were substantial, with the list of issues originally running to 64 issues in relation to the Process Claim and 17 issues in relation to the Modifications Claim.

Throughout the proceedings, the claimants advanced numerous serious allegations against the defendant and the interested parties, including allegations of bias, conflicts of interest, pre-determination of the competition outcome, retrospective amendment of reasoning to “retrofit” feedback to scores already awarded, and preferential treatment of Allwyn in the provision of Phase One Feedback. Many of these allegations were abandoned shortly before or during trial, often without notice and without explanation. Issues were dropped at the outset of trial, at the outset of closing submissions, and even during closing submissions, frequently only after the court or the other parties drew attention to the fact that they had not been addressed or could no longer be maintained.

The judgment, handed down by Mrs Justice Joanna Smith DBE, found against the claimants on all material issues. The consequentials hearing took place on 22 May 2026, at which the costs issues described below fell to be determined. By that stage, the claimants were represented by Mr Roger Mallalieu KC, without the assistance of any of their trial counsel. The defendant was represented by Ms Sarah Hannaford KC, Ms Rachael O’Hagan, and Mr Barney McCay, and the interested parties by Mr Mark Howard KC, Mr Malcolm Birdling KC, and Mr Jamie Carpenter KC.

Costs Issues Before the Court

Two principal costs issues required determination at the consequentials hearing.

The first was whether the defendant and the interested parties were entitled to recover their costs on an indemnity basis rather than the standard basis. It was common ground that the claimants were liable to pay the costs of both the defendant and the interested parties on a standard basis. The dispute was as to whether the basis of assessment should be elevated to an indemnity basis. The defendant and the interested parties sought indemnity costs in respect of the entirety of the proceedings, covering both the Process Claim and the Modifications Claim. The claimants conceded realistically that there were grounds for an indemnity costs order in respect of the costs of the trial of the Process Claim, or perhaps the costs of the Process Claim from the date of the pre-trial review, but contended that standard costs should apply to everything else, including the Modifications Claim in its entirety and the Process Claim up to the pre-trial review or the start of trial.

The second issue was whether the court should depart from the general rule that the winning party recovers all of its costs, by making a reduction to the defendant’s recoverable costs to reflect what the claimants characterised as an unreasonable approach to disclosure. The claimants sought a reduction to the defendant’s costs on the basis that the defendant’s conduct of the disclosure exercise had substantially increased the costs of all parties. The figure sought shifted between the witness evidence and the skeleton argument: the thirteenth statement of Mr Bryant suggested a 7.3% reduction, while the skeleton argument for the hearing proposed a 20% reduction for the first time, which would have had the effect of reducing the defendant’s costs bill by approximately £4 million. The application was made on 18 May 2026, four days before the hearing.

A third, more discrete point also arose concerning the extent of the interested parties’ involvement in the proceedings for the purposes of costs assessment, specifically whether the claimants could go behind the agreed list of issues, which had been annotated with references to the pleadings and had delineated the interested parties’ involvement throughout the trial.

The Parties’ Positions

On indemnity costs: The defendant and the interested parties submitted that the conduct of the claimants throughout the entirety of the proceedings was such as to take the case out of the norm and to warrant an order for indemnity costs across the board. They relied upon the cumulative effect of a number of factors: the inadequate and unparticularised pleadings from the outset; the broad and scattergun nature of the allegations, which included serious allegations of impropriety and dishonesty; the repeated and unexplained abandonment of issues and allegations, often at the last moment and without proper notice; the prejudice and disruption caused to the defendant and the interested parties by those abandonments; the unpleaded and fluctuating nature of the allegations advanced at trial; and the weak and speculative character of the claims from the beginning. Ms Hannaford KC submitted that the conduct warranting indemnity costs was not confined to the trial itself, because the conduct at trial was itself a consequence of the highly unreasonable manner in which the proceedings had been advanced from the outset. Mr Howard KC submitted that there was a need for the court to mark its disapproval of the claimants’ conduct by making an order for indemnity costs.

The claimants, through Mr Mallalieu KC, conceded realistically that there were grounds for an indemnity costs order in respect of the costs of the trial of the Process Claim, or at least from the date of the pre-trial review. However, they argued that standard costs should apply to the Modifications Claim in its entirety and to the Process Claim up to the pre-trial review or the start of trial. Mr Mallalieu also submitted that the defendant’s and interested parties’ costs were extremely high and raised proportionality as a relevant consideration in the exercise of the court’s discretion, arguing that the disproportionate level of those costs was a factor that should weigh against an indemnity costs order. He further cautioned the court against the exercise of hindsight in assessing the reasonableness of the claimants’ conduct.

On departure from the general rule: The claimants submitted that the defendant’s approach to disclosure had substantially increased the costs of all parties and that it would be unreasonable or unjust to require them to bear those increased costs. The application was advanced through the thirteenth statement of Mr Bryant, initially proposing a 7.3% reduction, with the skeleton argument for the hearing escalating that figure to 20% without adequate explanation. The claimants relied on the principles set out in TMO Renewables v Timothy Yeo [2021] EWHC 2773 (Ch), [2021] Costs LR 947.

The defendant, through Ms Hannaford KC, characterised Mr Bryant’s witness statement on the subject as “extremely thin” and submitted that the application was little more than a last-ditch attempt to obtain a reduction in the defendant’s costs. The defendant noted that it had had no proper opportunity to put in evidence in response to the application, given the very late service of the witness statement. The defendant also confirmed that it had excluded from its overall costs application both existing costs orders made during the proceedings and costs incurred in relation to the inadvertent disclosure of privileged documents, and that these would not be added back at a later stage.

The Court’s Decision

Indemnity costs: Mrs Justice Joanna Smith DBE ordered that both the defendant and the interested parties were entitled to recover their costs on an indemnity basis in respect of the entirety of the proceedings, covering both the Process Claim and the Modifications Claim.

The applicable principles were not in dispute. The court referred to Three Rivers DC v Bank of England [2006] EWHC 816 (Comm) at [25] per Tomlinson J, which cited Excelsior Commercial and Industrial Holdings Ltd v Salisbury Hammer Aspden & Johnson [2002] EWCA Civ 879, and to the summary of the law in Hislop v Perde Kaur [2018] EWCA Civ 1726 per Coulson LJ at [35] to [36]. Essentially, there must be conduct which takes the case out of the norm. That is a highly fact-sensitive question and the court’s discretion is extremely wide. The touchstone is unreasonableness, but that unreasonableness must be “to a high degree”. Unreasonable in this context does not mean merely wrong or misguided in hindsight. The court may have regard to an aggregation of factors and there are infinite situations that may give rise to highly unreasonable conduct.

The court found that this was a huge and important claim, billed by the claimants as “the most financially significant procurement process in UK history”. The claimants sought damages of over £1 billion together with a declaration of ineffectiveness which, if granted, would potentially have brought the National Lottery to a standstill. One would expect such a significant and substantial claim to be advanced in a serious, responsible, and proper manner. That was not what happened.

The court noted its observation in the main judgment that, notwithstanding the size of the claim and the legal resources available, the Process Claim had been advanced by the claimants in an apparently unfocused manner, leading to various of the numerous original issues being dropped at the outset of trial, at the outset of closing submissions and even during closing submissions. In many cases, the issues were not dropped until it was specifically drawn to the claimants’ attention by the court or by the other parties that they had not been addressed in the claimants’ written closing submissions or that there no longer seemed to be any viable basis on which they could be maintained. The extent of this moveable feast was regrettable and, given the legal resources available to the claimants, inexcusable. It led to significant time being wasted by the other parties in dealing with issues which were subsequently abandoned. It also risked leaving the court with an imperfect understanding of how the case was being advanced. The court described this as surprising, given the nature and alleged value of the claim, which would be an understatement.

There were numerous serious and wide-ranging allegations, including of impropriety and dishonesty, made by the claimants running through the litigation from the outset. These included allegations of: bias against the defendant as a whole and against specific individuals working for the defendant; conflicts of interest of varying types; pre-determination by the defendant’s Evaluators of the outcome of the Competition leading to only a perfunctory review at moderation; amendments to the defendant’s reasoning after the award decision was made but before it was communicated to the applicants so as to “retrofit” the feedback and comments to the scores awarded; and preferential treatment of Allwyn by the defendant in the provision of Phase One Feedback. These allegations were all advanced over an extended period of time. Many of them were only dropped shortly before or at the trial in wholly unsatisfactory and unreasonable circumstances.

By the end of trial, the list of issues, which originally ran to 64 issues in relation to the Process Claim and 17 issues in relation to the Modifications Claim, had been very substantially reduced, often without any proper notice being given to the other parties. This was, in the court’s judgment, highly unreasonable and wholly out of the norm. The court observed that no explanation had ever been provided by the claimants for their abandonment of any of the issues, nor had any reason been given by them for what the court considered to be a cavalier and highly unusual and unreasonable way of proceeding.

One of the most serious of the allegations made in the Modifications Claim was that the need for the Challenged Modifications was brought about “wholly or substantially by Allwyn’s failures to meet its obligations under the Enabling Agreement”, an allegation which was taken seriously by Allwyn, but mysteriously abandoned by the claimants without explanation during the course of the trial.

In addition to these numerous, serious, and wide-ranging allegations, the scale of the abandonments caused very significant disruption to the court and to the other parties, which the court considered to be out of the norm. It caused significant prejudice to the other parties in terms of their defence of the proceedings, in particular their understanding as to the case that was being advanced against them and the costs they had spent in trying to address that case. It also made it difficult for the court to understand the way in which the case was being advanced. At times, it was advanced in a fluid and apparently fully flexible and opportunistic manner.

Indeed, the claimants advanced a number of wholly unpleaded and unparticularised allegations at the trial and frequently sought to amend and reformulate existing allegations in a manner which the court considered also fell well outside the norm. The court commented on this approach in numerous places in the judgment. At [746] the court observed that the claimants had been forced in light of their abandonments “to reformulate (and often to reinvent their case) at every opportunity” throughout the trial. The court observed that this appeared to be a strong indicator that there was “really no basis whatever for [the] claim of manifest error or, indeed, therefore, for the intervention of the court”.

The court considered that the claimants advanced weak and speculative allegations in respect of both the Process Claim and the Modifications Claim from the outset. They pursued these all the way to trial notwithstanding that they had been notified by the defendant that those claims were doomed to fail from early in 2023. In the Process Claim the claimants had to overcome an almost insuperable hurdle: they had to establish that The New Lottery Company Limited would have passed every one of the 12 Pass/Fail Areas in respect of which it was failed during the Competition and that Camelot and Allwyn should both have been disqualified. The issue of standing, which the court found against the claimants in the Process Claim, meant that, absent proper evidence as to the counterfactual, the Modifications Claim could not succeed. Yet, the claimants fought the Modifications Claim (which it is now accepted was intertwined with the Process Claim) without such evidence. The court also agreed with Ms Hannaford KC that the Modifications Claim was always very weak in its own right owing to The New Lottery Company Limited’s woeful performance in the fourth National Lottery competition, the gap between its score and the scores of Allwyn and Camelot being 30%.

Mr Mallalieu correctly cautioned the court against the exercise of hindsight, and the court considered whether any of these matters might be affected by hindsight, but agreed with Ms Hannaford that hindsight did not affect the analysis in this case given the way in which the trial and case had proceeded from the outset.

Individually or cumulatively, the matters identified by the court were, in its judgment, highly unreasonable and took the case out of the norm. The court relied upon the many detailed points made in the judgment as to the claimants’ poor and unparticularised pleadings, their abandonment of claims, the prejudice and disruption caused by these abandonments, the extent of the unpleaded and fluctuating allegations and the weak and speculative nature of the claims.

The court did not accept the claimants’ evidence in the thirteenth statement of Mr Bryant that they were not to blame for the approach they took to the litigation or that their conduct was the consequence of circumstances imposed upon them. The court also did not consider it to be appropriate to “salami slice” the orders for costs by reference to individual issues or periods of time, as Mr Mallalieu suggested. The court accepted Ms Hannaford’s submissions that the conduct of the claimants which warranted an order for indemnity costs was not just their conduct at trial, because that conduct was itself a consequence of the highly unreasonable way in which these proceedings had been advanced and pursued from the beginning. The pleadings were inadequate and unparticularised from the outset, the claims were weak and none of these issues was remedied prior to trial. The pleadings gave no proper indication to the defendant and the interested parties as to the case that they must meet. The allegations made by the claimants, as Mr Howard KC said, were broad and scattergun because there did not appear to be a realistic pleaded case. They were not supported by adequate evidence from the claimants. Yet the defendant and the interested parties had to expend very considerable amounts of money in preparing to meet those allegations as best they could, only to find them being peremptorily abandoned or changed at trial.

Accordingly, the conduct that the court found to be highly unreasonable was conduct running through the whole of the case. It plainly warranted an order for indemnity costs in relation to the entirety of the proceedings. Further, the court agreed with Mr Howard that there was a need to mark disapproval on the part of the court of such extraordinary conduct by the making of such an order.

During the course of his submissions, Mr Mallalieu suggested that the defendant’s and interested parties’ costs were extremely high, that there were issues arising in relation to their proportionality, and that this was a relevant consideration to take into account in the exercise of the court’s discretion. Specifically he prayed in aid the disproportionate nature of those costs in seeking to persuade the court not to award costs on an indemnity basis. However, the court rejected that submission. The court stated that there is nothing in the authorities to suggest that proportionality is a relevant factor in considering whether to make an order for indemnity costs and that it was inclined to think that it is not. If a party has conducted itself in a highly unreasonable fashion which is out of the norm so as to justify the award of indemnity costs, that party has forfeited the right to any assessment based on arguments of proportionality. In any event, even if the court was wrong about that, it did not consider that Mr Mallalieu’s arguments on proportionality would have shifted the dial given the serious and highly unreasonable nature of the conduct in this case. The conduct here was such that there was no injustice in the claimants being unable to challenge the quantum of the other parties’ costs on the grounds of proportionality.

Departure from the general rule: The court turned to deal with the claimants’ application for the court to depart from the general rule that the winning party should recover all of its costs. The claimants sought an order for a reduction to the defendant’s costs to reflect various issues that they had identified with the disclosure exercise, as explained in the thirteenth statement of Mr Bryant. In short, the claimants submitted that the defendant’s approach to disclosure had substantially increased the costs of all parties involved and that it would be unreasonable or unjust to expect them to pay those increased costs.

The court was referred by Mr Mallalieu to the relevant principles in relation to the approach to costs, which are set out in the case of TMO Renewables v Timothy Yeo [2021] EWHC 2773 (Ch), [2021] Costs LR 947 at [7] to [14]. The court bore those in mind, but did not need to recite them. In the evidence of Mr Bryant, it was suggested that there should be a 7.3% reduction of the defendant’s costs to reflect the unreasonable costs incurred during disclosure. However, in the claimants’ skeleton argument for the hearing it was suggested for the first time that there should be a 20% reduction. No adequate explanation was given as to why that should be the case.

Having considered the arguments, the court was not prepared to make any reduction to the defendant’s costs. Having regard to all the circumstances of this case, the court considered justice to require that the defendant, as the winning party, should be entitled to recover all of its costs.

This application was made only on 18 May (the hearing being on 22 May) in the witness statement of Mr Bryant. Ms Hannaford described Mr Bryant’s witness statement on the subject as “extremely thin”, and the court agreed. No adequate explanation for the proposed reduction had been given. The defendant had had no proper opportunity to put in evidence in response to the application, which the court considered to be unfair, and the court bore in mind that the judgment in this matter had been handed down over a month ago and that this consequentials hearing was taking place, therefore, some considerable time after receipt of the judgment. If an application for a 20% reduction (or any reduction) from the defendant’s costs was to be made, it should have been made with proper notice being given to the defendant.

The court agreed with the defendant that this was little short of a last-ditch attempt on the part of the claimants to obtain a reduction of the defendant’s costs. A reduction of 20% would have the effect of slicing around £4 million from the defendant’s cost bill. The court did not consider there to be any basis for such an order, nor did it consider it to be fair, just or in accordance with the overriding objective to make that order.

The defendant had excluded both existing costs orders made during the course of the proceedings and costs incurred in relation to its inadvertent disclosure of privileged documents from its overall application for indemnity costs. It had confirmed that these would not be added back later. If the defendant spent an unreasonable amount of time on disclosure, that could be addressed on the assessment of costs. The court accepted that there were difficulties in this case with disclosure, but bore in mind that the issues raised in these proceedings necessitated a substantial and complex disclosure exercise. Disclosure in tranches was the subject of court orders, including as to costs. That was not unusual in a case of this magnitude and the court did not consider the disclosure issues identified by the claimants to go beyond what one would expect to see in the ordinary cut and thrust of litigation of this type.

Accordingly, in the exercise of its discretion and having regard to the relevant principles and the overriding objective, this was not a case in which the court should depart from the general rule that the losing party must pay all of the winning party’s costs.

The extent of the interested parties’ interests in the proceedings: Finally, the court observed that the extent of the interested parties’ interest in these proceedings was agreed by the parties in the list of issues which was annotated with relevant references to the pleadings. The trial proceeded on the basis that the list of issues accurately identified and delineated the interested parties’ involvement. The court did not consider there now to be any scope for the claimants to go behind that identification and delineation when it comes to the assessment of costs.

▶ Watch the case summary

Indemnity Costs And The High Risk Of Pursuing A Weak Case

Costs Thrown Away, Indemnity Costs And Payments On Account

Dishonest Evidence And Baseless Allegations Justify Indemnity Costs Order

Indemnity Costs | Be Reasonable

Probate Challenger Ordered To Pay Indemnity Costs After Maintaining Baseless Opposition For Eight Years

Costs On Indemnity Basis For Wasted Hearing Due To Unreasonable Adjournment Application

The Commercial Court’s decision in Diageo DV Limited v NIO S.R.L. (in liquidation) [2026] EWHC 1198 (Comm) addresses the recovery of foreign litigation costs as damages for breach of an exclusive jurisdiction agreement and the assessment of such costs on the indemnity basis.

Background

This matter concerned an application by Diageo DV Limited (“Diageo”), an English company engaged in the production and distribution of alcoholic beverages, for summary judgment and a final anti-suit injunction against NIO S.R.L. (in liquidation) (“Nio”), an Italian company in voluntary liquidation. The application was heard on 17 April 2026 before Anna Dilnot KC, sitting as a Deputy High Court Judge in the Commercial Court, with judgment handed down on 19 May 2026.

The underlying dispute arose from a Share Purchase Agreement dated 23 November 2023 (the “SPA”), by which Diageo agreed to purchase Nio’s category “A” share in Niococktails s.r.l. (“Niococktails”) for consideration comprising a completion payment of €2.75 million, a deferred payment of €1.25 million, and a contingent exit payment of at least €1 million. The dispute centred on Diageo’s decision to withhold €780,008 from the deferred payment, representing its estimated liability in respect of a settlement reached between Niococktails and entities associated with Conor McGregor and Proximo Spirits Inc (together, the “Proximo/McGregor Entities”).

Prior to the SPA, in around August 2023, Niococktails had entered into a letter of intent and a promotional services agreement with the Proximo/McGregor Entities. Following completion of the share purchase, those arrangements were terminated, prompting the Proximo/McGregor Entities to threaten claims of up to USD 12 million against Niococktails. A settlement agreement was ultimately executed on 2 August 2024, with Niococktails paying USD 1 million in full and final settlement. Diageo subsequently notified Nio of its intention to withhold part of the deferred payment as an estimated liability under clause 6.2 of the SPA.

By letter dated 18 November 2024, Diageo gave notice that it intended to withhold €800,000 from the deferred payment, incorrectly stating the settlement sum as €1 million. Diageo corrected that error in a letter dated 28 November 2024, explaining that the estimated liability was €750,000, being USD 1 million less the €200,000 excess stipulated by clause 7.5(a) of the SPA, converted to euros at an exchange rate of USD 1:EUR 0.95. On 14 January 2025, Diageo paid Nio €469,992, being the deferred payment of €1.25 million less €780,008, the latter figure representing the settlement sum less the excess, converted to euros using the Bank of America spot rate at the date of payment.

Nio objected to the withholding, raising grounds including alleged failures by Diageo to provide sufficient information, non-compliance with clause 5.4 of the SPA (which required reasonable endeavours to settle by way of a product purchase from Proximo), and the contention that Diageo had no unilateral right to withhold any sum without prior agreement or a determination under the Counsel Determination Mechanism provided for in clause 6.2. The parties exchanged correspondence between November 2024 and January 2025 without reaching agreement, and neither party invoked the Counsel Determination Mechanism.

On 26 March 2025, Nio commenced proceedings before the Civil Court of Milan, seeking recovery of the withheld sum. Nio relied upon an exclusive jurisdiction clause in favour of the Italian courts contained in Article 8 of a Deed of Transfer dated 1 December 2023, which had been executed to satisfy the formal requirements of section 2470 of the Italian Civil Code for the transfer of shares in an Italian company. Nio also filed an application before the Italian Supreme Court seeking a declaration that the Milan court had jurisdiction, which resulted in the Milan proceedings being stayed.

Diageo’s position was that the SPA contained, at clause 24.2, an exclusive jurisdiction agreement in favour of the English courts, and that the Italian proceedings had been commenced and pursued in breach of that agreement. Diageo obtained an interim anti-suit injunction from David Bailey KC on 18 July 2025 (reported at [2025] EWHC 2109 (Comm)), restraining Nio from taking further steps in the Italian proceedings. That injunction was continued until further order by HHJ Pelling KC by order dated 8 September 2025, which also addressed service of the claim form and other documents on Nio out of the jurisdiction in Italy. HHJ Pelling KC also made a costs award in Diageo’s favour at that stage in the amount of £85,159 (from a claimed sum of £95,411), covering the costs of the hearing before David Bailey KC and the application to continue the interim injunction, assessed on the indemnity basis.

Diageo’s application for summary judgment and a final anti-suit injunction was issued on 6 January 2026 and served on Nio by certified email on 23 January 2026. Nio did not file any acknowledgement of service or defence, and did not appear or seek representation at the hearing on 17 April 2026. The court was satisfied that Nio had been properly served and was aware of the application, and proceeded to determine it in Nio’s absence.

Costs Issues Before the Court

Three distinct costs matters fell to be determined. The first was whether Diageo was entitled to recover, by way of damages, the legal costs it had incurred in the Italian proceedings as a result of Nio’s breach of the exclusive jurisdiction clause in the SPA. The second was whether an interim payment on account of those damages should be made at this stage, given that the Italian proceedings remained ongoing and the full extent of Diageo’s loss could not yet be quantified. The third was the summary assessment of the costs of the application before the court on the indemnity basis.

On the question of damages, the legal basis for recovering foreign litigation costs as damages for breach of an exclusive jurisdiction clause was well established. The court noted that the proposition had gone unchallenged before the Supreme Court in both Starlight Shipping Co v Allianz Marine and Aviation Versicherungs AG [2013] UKSC 70 and AMT Futures Ltd v Marzillier [2018] AC 439. The measure of recovery is to put the non-defaulting party in the position it would have been in had the foreign proceedings not been brought at all, and can include costs incurred in those foreign proceedings: Compania Sud Americana de Vapores SA v Hin-Pro International Logistics Ltd [2015] 1 Lloyd’s Rep 301 at [37] to [38]. Importantly, such costs are recoverable even where the foreign court lacks the power to award costs: Union Discount Co Ltd v Zoller [2002] 1 WLR 1517 at [31]. The assessment of those costs is conducted on the indemnity basis, with the burden of establishing any failure to mitigate resting on the party in breach: National Westminster Bank plc v Rabobank Nederland (No. 3) [2008] 6 Costs LR 839 at [25].

On the question of the costs of the English proceedings and application, the court noted that a successful claimant for an anti-suit injunction is ordinarily entitled to its costs on the indemnity basis where it can establish that the breach of the exclusive jurisdiction clause caused it reasonably to incur legal costs: A v B [2007] 2 CLC 203 at [9] to [15]. Diageo sought summary assessment of the costs of the application on the indemnity basis, having provided a costs schedule in that regard. The court also had to consider how to treat any costs of the proceedings falling outside the scope of the two earlier applications and the present application, given the prior costs order made by HHJ Pelling KC.

The Parties’ Positions

Diageo’s position on damages was that, by commencing and pursuing the Italian proceedings in breach of clause 24.2 of the SPA, Nio had caused Diageo to incur costs in Italy in challenging the jurisdiction of the Italian courts. Those costs were recoverable as damages. Diageo was not yet in a position to quantify its total loss, given that the Italian proceedings remained ongoing, with the Milan court proceedings stayed pending the Italian Supreme Court’s determination on jurisdiction. Diageo therefore sought an interim payment of damages pursuant to CPR 25.20 and CPR 25.23(b) in the amount of £44,045, representing approximately 90% of the costs totalling €52,238.29 incurred to date in the Italian proceedings. Those costs were evidenced by invoices from Diageo’s Italian lawyers, PedersoliGattai. Diageo also sought an order that the remainder of its damages be assessed following the conclusion of the Italian proceedings.

On the costs of the application, Diageo sought summary assessment on the indemnity basis in the sum of £42,056.90. Diageo submitted that it was entitled to costs on the indemnity basis as a successful claimant for an anti-suit injunction, the breach of the exclusive jurisdiction clause having caused it reasonably to incur legal costs in obtaining the relief granted.

Nio did not appear and was not represented at the hearing. It had not filed any acknowledgement of service or defence, and had not responded to the application other than to dispute service in correspondence.

The Court’s Determination

The court granted summary judgment in Diageo’s favour, finding that Nio had no real prospect of successfully defending the claim. The court found that clause 24.2 of the SPA constituted an exclusive jurisdiction agreement in favour of the English courts. The court rejected Nio’s reliance on the jurisdiction clause in the Deed of Transfer, finding that the Deed was narrow in scope and concerned only with the formalities for effecting the transfer of the share in Niococktails. The construction of the exclusive jurisdiction clause started from the assumption, established in Fiona Trust & Holding Corp v Privalov [2007] UKHL 40, that the parties, as rational business people, are likely to have intended any dispute arising out of the relationship into which they have entered to be decided by the same tribunal unless the language of the clause makes it clear that certain questions are to be excluded from that tribunal’s jurisdiction. The Deed was not concerned with the wider rights and obligations of the parties related to the sale and purchase, including the terms upon which any part of the deferred payment could be withheld. All of the claims brought by Nio before the Court of Milan were disputes or claims which fell within the material scope of clause 24.2 of the SPA. While labelled by Nio as claims for breaches of the Deed of Transfer or of provisions of Italian law, they were in substance claims for breaches by Diageo of the terms of the SPA or the non-fulfilment of the conditions required to be fulfilled before Diageo was entitled to withhold any part of the deferred payment.

The court granted a final anti-suit injunction restraining Nio from continuing with the Italian proceedings, both before the Court of Milan and the Italian Supreme Court. The court also granted declaratory relief confirming that the claims brought by Nio in the Italian proceedings were within the scope of the exclusive English jurisdiction agreement and were brought in breach of that agreement.

On the substantive dispute, the court found that Diageo had complied with its obligations under clause 5.4 of the SPA (including the obligation to use reasonable endeavours to ensure Niococktails gave due regard to settling by way of a product purchase from Proximo, and to consult with Nio prior to entering into the settlement agreement). The court also found that Diageo had complied with clause 6.2 of the SPA and was entitled to withhold the sum of €780,008 from the deferred payment as a genuine and bona fide estimate of Nio’s liability under the indemnity provision. The court rejected Nio’s argument that Diageo was not entitled unilaterally to withhold any amount without agreement or a prior determination via the Counsel Determination Mechanism, finding that clause 6.2 entitled Diageo to withhold the amount of the estimated liability as long as it had notified Nio of the same in writing before the deferred payment became due.

Damages for Italian Litigation Costs

The court held that by commencing and pursuing the Italian proceedings, Nio had breached the exclusive jurisdiction clause in the SPA. As a result of that breach, Diageo had taken steps in Italy to challenge the jurisdiction of the Italian courts and had incurred costs, principally legal costs. The court considered that Diageo was entitled to recover such expenditure which was reasonably incurred as damages in the proceedings.

The court applied the principles established in Union Discount Co Ltd v Zoller and National Westminster Bank plc v Rabobank Nederland (No. 3). A party forced to defend proceedings brought in breach of an exclusive jurisdiction clause can recover reasonable costs incurred as a result of the foreign proceedings even if the foreign court lacks the power to award costs. The assessment of those costs is conducted on the indemnity basis such that the non-defaulting party can recover all costs reasonably incurred and reasonable in amount, with the burden of proof of any failure to mitigate on the party in breach. The court described the indemnity basis as “a useful proxy for an exercise in assessing reasonable costs where the burden is on Nio to establish a lack of reasonableness or failure to mitigate,” drawing an explicit analogy with the burden of proof under CPR 44.3(3).

Diageo was not in a position finally to determine the amount of its loss because the Italian proceedings were ongoing, with the proceedings before the Milan court stayed pending a decision on jurisdiction from the Italian Supreme Court. The court therefore considered it appropriate to grant an interim payment of damages.

The sum of £44,045 sought by Diageo represented approximately 90% of the costs (which totalled €52,238.29) that Diageo had incurred to date in respect of the Italian proceedings. Those costs had been established by way of the invoices submitted by Diageo’s Italian lawyers, PedersoliGattai. The court acknowledged that even assessing the costs on the indemnity basis, 90% would be a high proportion of costs to recover. However, the amount of £44,045 was reasonably modest and the court had no specific reason to reduce the amount of the interim payment sought. Further, it was likely that Diageo would continue to incur legal costs in Italy and it followed that its final costs burden for which it would be entitled to be compensated would likely exceed £44,045.

The court therefore granted Diageo an interim payment in the amount of £44,045, with the remainder of its loss to be assessed in due course following the conclusion of the Italian proceedings. The court considered it appropriate for Diageo to receive some contribution from Nio towards its costs at this point rather than awaiting the conclusion of the Italian proceedings.

Summary Assessment of Application Costs

The court turned to the costs of the application before it. Diageo had been provided with a costs schedule in respect of the application (but not the proceedings), with a request that costs be assessed summarily and on the indemnity basis. The total amount claimed as the costs of the application was £42,056.90.

The court noted that HHJ Pelling KC had already made a costs award in Diageo’s favour in the amount of £85,159 (out of the £95,411 claimed) which sum covered Diageo’s costs of the hearing before David Bailey KC on 18 July 2025 and the costs of the application to continue the interim anti-suit injunction, assessed on the indemnity basis. The court observed that it was unclear whether there existed costs of the proceedings (other than the £10,000 court fee for issuing the proceedings) which fell outside of the scope of those two applications, this application and the Italian proceedings.

The court therefore limited its summary assessment to the costs of this application (plus the £10,000 court issue fee), with any other amounts incurred by Diageo in the proceedings not already subject to costs orders to be assessed at the same time as damages were finally to be assessed. The court assessed the costs of the application on the indemnity basis in the amount of £33,645, being 80% of £42,056 (the judgment uses the rounded figure of £42,056 at paragraph 87, though the claimed sum stated at paragraph 86 is £42,056.90). The court did not provide reasons for the 20% reduction in its judgment.

YouTube player

 

Claiming costs in one action as damages in another

When Should Costs Be Awarded In A Foreign Currency? Supreme Court Rejects ‘Loss Reflection’ Test

Indemnity Basis Costs Following Discontinuance

Costs Thrown Away, Indemnity Costs And Payments On Account

Section 51 Costs Jurisdiction Injunction Without Claim Form | Gotti

Payments On Account In Budgeted Cases And Pre Judgment Interest On Costs

 

The Technology and Construction Court’s decision in MJS Projects (March) Limited v RPS Consulting Services Limited [2026] EWHC 884 (TCC) addresses whether a successful defendant’s conduct in refusing mediation and its expert’s late change of evidence justified departing from the usual costs rule.

Background

This costs judgment arose from the dismissal of a professional negligence claim brought by MJS Projects (March) Limited against RPS Consulting Services Limited in the Technology and Construction Court in Leeds. The underlying dispute concerned the design and construction of a container park near Felixstowe Port, with the Claimant alleging that the Defendant’s design fell below the standard of a reasonably competent firm of civil and structural engineers. The court ultimately found in favour of the Defendant, concluding that the cause of the damage was workmanship rather than design.

The pre-action history was protracted. The Defendant’s letter of response, dated 22 May 2019, set out in considerable detail why it considered its design was not negligent and identified eleven workmanship defects, as well as the use of incorrect dowel sizes. The Claimant’s response, dated 5 November 2019, did not engage with those workmanship allegations and instead requested sight of the Defendant’s calculations. Those calculations were provided by letter dated 22 December 2020. No substantive reply was received for nineteen months. When the Claimant wrote again in July 2022, it confirmed that an expert structural engineer had been instructed and that the expert supported the Claimant’s position on design negligence. Proceedings were issued on 14 October 2022. Particulars of Claim were served on or around 10 February 2023, a Defence on or around 14 April 2023, and a Reply on 19 May 2023.

The expert evidence timetable was, as the court described it, “concertina-ed” into a short period before trial. The experts’ joint statement was produced approximately three months before trial, with individual expert reports following thereafter. Supplementary reports were filed in response to points raised in the primary reports, with some material served as late as one week before the trial commenced in February 2024. The claim was dismissed following trial, and the costs and consequential orders hearing took place on 14 May 2025, with judgment handed down on 15 April 2026.

Costs Issues Before the Court

Three distinct costs issues required determination. The first was whether the usual costs order, namely that the unsuccessful Claimant pay the Defendant’s costs, should be departed from on account of the Defendant’s conduct in relation to alternative dispute resolution. The Claimant argued that the Defendant had unreasonably refused to engage in mediation on multiple occasions, both before and after proceedings were issued, and that this conduct justified a departure from the default position under CPR 44.2. The Claimant’s position was that the appropriate order was no order as to costs.

The second issue was whether the Defendant’s expert having changed his position on the mass concrete taper and having produced additional calculations approximately one week before trial constituted conduct that should further influence the costs order in the Claimant’s favour.

The third issue was the Defendant’s cross-application for indemnity costs in respect of the expert evidence phase of the proceedings. The Defendant contended that the conduct of the Claimant and its legal team in relation to the instruction, oversight, and management of the Claimant’s expert was sufficiently outside the norm to justify an order for costs on the indemnity basis for that phase. In the alternative, both parties agreed that a payment on account of costs should be made, with the only dispute being the appropriate percentage reduction to apply to the approved costs budget.

The Parties’ Positions

The Claimant’s position on ADR

The Claimant traced a series of proposals for mediation made from as early as 14 July 2022, when a without prejudice meeting, mediation, or meeting of experts was suggested. That proposal was declined by the Defendant on 30 September 2022 on the basis that mediation was not appropriate until the Claimant had provided its expert report. Further proposals were made on 5 June 2023 and 21 September 2023, the latter suggesting two named mediators and a mediation in late October or November 2023. The Defendant declined that proposal by letter dated 28 September 2023, citing the technical nature of the issues and the fact that liability was denied in full, and suggesting that any mediation should follow the experts’ joint statements due in November 2023.

The Claimant characterised the Defendant’s successive objections as a shifting of the goalposts: first, no mediation until the expert report was provided; then, no mediation until after expert discussions; then, no mediation without the experts present at the mediation itself. The Claimant noted that its expert was based in Singapore, making expert attendance at a mediation impractical. It submitted that, applying the Halsey v Milton Keynes General NHS Trust [2004] 1 WLR 3002 factors, this was not a case unsuitable for mediation. Professional negligence disputes of this nature were routinely resolved at mediation, the parties’ budgets had each included approximately £25,000 for mediation costs, and the value of the claim at nearly £400,000 justified that expenditure. The Claimant also submitted that the merits were not entirely one-sided, given that the Defendant’s expert had changed his position on the mass concrete taper and that the outcome might have been different but for the late additional calculations.

The Claimant’s position on the expert’s late change of evidence

The Claimant submitted that the Defendant’s expert had stated in his written evidence that the mass concrete taper was part of the design and that the failure to install it was a workmanship defect causing the cracking. At trial, he accepted that the mass concrete taper was not part of the design at the relevant joints. The Claimant argued that it had been entitled to approach trial on the basis that the Defendant’s expert would give evidence consistent with his written report and the joint statement. The Claimant asserted that the expert changed his mind as a result of very late additional calculations produced one week before trial, and that this late change of position had a decisive impact on the outcome. On that basis, it was submitted that it would be unjust for the Defendant to recover all of its costs.

The Claimant’s position on indemnity costs

The Claimant resisted the indemnity costs application on the basis that the threshold was high and had not been met. It submitted that the correct Bolam question had in fact been put to the expert in his letter of instruction and was set out on the face of his report. The fact that the expert appeared under cross-examination not to have applied the test correctly did not amount to conduct unreasonable to a high degree. The Claimant also relied on the compressed expert evidence timetable, noting that reports were served late and that supplementary reports followed in quick succession. It was submitted that the expert’s decision to rerun the FE analysis immediately before trial, without informing anyone, could not be attributed to the Claimant or its lawyers, as everyone was astonished when the expert disclosed this during his evidence. The Claimant argued that the tactical decision to focus on design negligence rather than workmanship, whilst ultimately unsuccessful, was a legitimate forensic choice and did not take the conduct of the litigation outside the norm.

The Defendant’s position on ADR

The Defendant accepted the broad outline of the correspondence but submitted that the full chronology had to be considered. It emphasised that workmanship issues had been raised as the cause of the damage for four years before proceedings were issued, and that the Claimant had never substantively engaged with those allegations. The Defendant had provided detailed calculations when requested, had engaged fully in the pre-action protocol process, and had made Calderbank offers and Part 36 offers in the run-up to trial. It submitted that it was not refusing to engage in ADR but was reasonably requiring some understanding of the Claimant’s expert evidence before committing to a mediation process. It noted that the Claimant had refused to provide its expert report even on a without prejudice basis, and that the Claimant’s own stance immediately before trial, asserting that its Part 36 offer “was not made for negotiation purposes” and that it had “a strong case”, demonstrated that mediation would not have had realistic prospects of success. The Defendant also pointed to the Claimant’s imposition of onerous conditions on any mediation, including that the Defendant would have no say in the identity of the mediator appointed, and argued that the Claimant’s refusal to engage with workmanship allegations throughout the pre-action period made meaningful mediation impossible without expert evidence being available.

The Defendant’s position on the expert’s late change of evidence

The Defendant submitted that the mass concrete taper issue had limited materiality. The Particulars of Claim did not mention a mass concrete taper and did not assert that the failure to specify one was a negligent defect in the design. It was never part of the Claimant’s case that a mass concrete taper was required. The issue was only first mentioned in the experts’ joint statement dated 15 December 2023, and the detail of the Defendant expert’s evidence on this aspect came in his report served on 26 January 2024, just over one week before trial. By this time, the majority of costs were already incurred. The Defendant’s expert had explained that a further check was required after consideration of some of the points raised by the Claimant’s expert, and the court accepted that explanation. The additional calculations did not cause the Claimant to abandon its case and did not result in additional costs being incurred. The Defendant also submitted that it was wrong to assert that the expert simply changed his evidence on the number of dowels engaged by the design when the court accepted his explanation that a further check was required.

The Defendant’s position on indemnity costs

The Defendant asserted that the conduct of the Claimant and its legal team in relation to the instruction, oversight, and management of the Claimant’s expert was sufficiently outside the norm to justify an order for costs on the indemnity basis for the expert phase. The Defendant criticised the fact that the Claimant’s expert did not directly answer the question of whether the Defendant’s design was one that a reasonable body of engineers could have produced. Proceedings were issued, the experts’ joint statement produced, and expert reports exchanged without that question being answered. The Defendant asserted that the Claimant did not properly interrogate the application of the Bolam test, the Defendant’s causation arguments, the significance of the date by which the damage had become manifest, nor provide any evidence about what the correct design would be if the Defendant’s design was negligent. The Defendant also criticised the Claimant’s expert’s decision to use FE analysis to assess the Defendant’s design, his use of an out-of-date edition of a technical publication without disclosing that fact, his changes of position without explanation, and his decision to rerun the FE analysis over the weekend before trial without informing anyone. All of these factors, the Defendant submitted, showed the inadequacy of the Claimant’s expert’s compliance with CPR 35 and his expert duty, and justified a costs sanction.

The Court’s Decision

Costs to follow the event

Her Honour Judge Kelly ordered that the Claimant pay the Defendant’s costs, to be the subject of detailed assessment if not agreed. The judge accepted that the Defendant had declined multiple mediation proposals but held that this could not be assessed in isolation. The full chronology had to be considered, including the Claimant’s failure to engage with workmanship allegations raised in 2019, the 19-month delay in responding to the Defendant’s calculations, and the refusal to provide expert evidence even on a without prejudice basis.

Applying the Halsey factors, the judge found that it was not unreasonable for the Defendant to have refused mediation before having some understanding of the Claimant’s expert evidence. The Defendant had raised workmanship issues in response to the letter of claim, and the Claimant had asked for calculations to justify the Defendant’s design but did not deal with the alleged workmanship issues. The Defendant’s calculations were provided, but the Claimant then did not respond for 19 months. When the Claimant wrote again, it stated it had expert support for its case but once more did not engage with the workmanship issues. The Defendant asked for a copy of the expert report on a without prejudice basis and again raised the lack of response to the issues about workmanship and causation. The Claimant did not provide the expert report and did not engage with workmanship issues in any meaningful way.

The judge accepted that the Defendant did not agree to the continued suggestions of mediation without having some understanding of the expert evidence, but held that this could not be described as unreasonable. Other forms of ADR were proposed by the Defendant throughout, and offers were being made. The nature of the dispute would not prevent a successful mediation, but having actively engaged, provided calculations and justification as to why the Defendant asserted it was not negligent, it was not unreasonable to require a meaningful response to the points made before mediation. Mediation may have cost up to £50,000, which was not an insignificant sum, especially when the Claimant was not providing information which was reasonably requested.

Once the expert evidence was available, the Claimant’s offer to consider mediation was only weeks before the start of the trial and was offered only on potentially disadvantageous terms to the Defendant. The judge held that failure to agree to earlier mediation, nor to the last suggestion of mediation on the terms demanded, could not reasonably be held against the Defendant. The Defendant’s reasoned rejection of one form of ADR, namely mediation, was not unreasonable. The legal issues were clear and largely agreed between the parties. The case would always depend upon the court’s assessment of the expert evidence. The Claimant’s refusal to disclose its expert evidence (even on a without prejudice basis) and its apparent failure to instruct its expert to consider all of the workmanship issues raised by the Defence would inevitably have had a significant impact on the likely success of any mediation.

Even had mediation taken place, the judge did not accept that it would have had reasonable prospects of success. The Claimant had not engaged with the Defendant’s allegations of poor workmanship nor provided its expert evidence. The Defendant’s reasonable wish to understand the case it was meeting was not just going to disappear. Offers were being made both ways in the run up to trial, but the parties remained a vast distance apart.

The expert’s late change of evidence

The judge did not accept the Claimant’s assertions that a “late change” of evidence by the Defendant’s expert supported a decision that no order as to costs was the appropriate costs order. The judge found that the Defendant’s expert was in error in asserting that a mass concrete taper was part of the Defendant’s design. However, as the need for a mass concrete taper was never part of the Claimant’s case that the Defendant’s design was negligent, this did not have a material bearing on the outcome of the litigation. The Claimant’s expert did not assert that a mass concrete taper was needed to make the design work. The first mention of the need for a mass concrete taper was about two months before trial when the experts produced their joint statement. The need for a mass concrete taper was only if adequate compaction could not be achieved under the relevant joint. The detail of the Defendant’s expert opinion on the need for a mass concrete taper came in his report served about one month before trial.

In both the joint statement and the report, the Defendant’s expert made it clear that he knew that the mass concrete taper was shown on the design drawing for a different joint. However, he was of the opinion that the Claimant’s workmen should have inferred that a mass concrete taper was also required under the relevant joint, even though it was not shown on the design drawings, because of the compaction issue. The Claimant’s expert opined that the necessary compaction could be achieved and that was the finding the judge made. The Defendant’s expert also produced some additional calculations shortly before trial. However, as was stated in the judgment, that was done to enable him to consider the evidence of the Claimant’s expert and the criticisms of the design and the conclusions drawn from them. The judge held this was classically an example of the sort of final “sense check testing” the court would expect from an expert, particularly when the expert evidence has been finalised very late in the day before trial. The judge accepted the Defendant’s submission that this was “simply part of the usual cut and thrust of a professional negligence trial”. In those circumstances, it was difficult to see how any additional costs were caused by the late calculations in any event.

Indemnity costs refused

The Defendant’s application for indemnity costs in respect of the expert phase was refused. The judge reminded herself that the question was whether there was something in the conduct of the action or the circumstances of the case which took the case out of the norm in a way which justified an order for indemnity costs. The judge was just persuaded that the answer to that question was no, and costs should be assessed on the standard basis throughout.

The judge had made findings in the substantive judgment that the Claimant’s expert did not properly understand his duties to the court pursuant to CPR 35, that he did not appear to have considered adequately the applicable legal test, and he did not deal with the workmanship issues raised by the Defendant adequately. He used an outdated edition of a technical publication to justify some conclusions without providing any reference to the updated edition. He carried out additional tests and reran the FE analysis immediately before trial without telling anybody he had done this nor providing anyone with the results. The Claimant lost the case because the judge had no confidence in its expert.

The judge agreed with the Defendant’s submission that this was not simply a case of the court preferring one expert’s evidence over another. The reality was that the criticism of this expert went beyond that. However, the judge accepted that the Claimant’s solicitors had put the correct test in the expert’s instructions, and the expert had set out the correct test in his written report and answered questions in a way which would indicate that he was considering the correct test when giving his opinion. When cross-examined, it became apparent that he was not correctly applying the test and had not given consideration to various matters to which the judge found he should have given consideration. The judge accepted that a claimant is responsible for their expert for the purposes of costs. However, she did not accept that there was sufficient material before trial in the expert’s reports to indicate to the Claimant’s legal team that their expert was going to give evidence in the way that he did. Further questions could perhaps have been asked of the expert during the proceedings. That may have been an error or a tactical decision. However, the judge did not accept that the asserted failure to spot the various problems with their expert’s evidence was sufficient to pass the high hurdle before indemnity costs are justified.

The Claimant made various tactical decisions in how to pursue its case against the Defendant for negligent design. Some tactical decisions would always be needed when a company associated with the Claimant has carried out the construction work for the design and that work is criticised by the Defendant as being the cause of the damage. With hindsight, it may have been better expressly to instruct the Claimant’s expert to deal with the various workmanship defects asserted by the Defendant. However, as the Claimant took the view that it only needed to prove that the defective design was “a” cause of the damage, it did not need to deal with all of those workmanship issues. The tactic was unsuccessful, but the judge accepted that deciding on the tactic did not take the Claimant’s lawyers’ conduct “out of the norm”.

It may have been that the Claimant’s legal team restricted its frame of reference in respect of the expert evidence required because of the analysis undertaken by John Frith. However, the tactic of concentrating primarily on identifying a negligent design and then establishing the negligent design was a cause of the damage, whilst unsuccessful, could not be said to take the conduct of the case so far out of the norm. The further criticisms of the Claimant’s lawyers, such as refusing to answer Part 18 further information questions, the judge would not find to justify indemnity costs. If the Defendant felt that the refusal to answer the questions was unjustified, it could have made an appropriate application.

The Claimant’s counsel asked for clemency for the Claimant’s expert as his reputation had been tarnished by the judgment, and he would have to live with the consequences of that. The judge did not accept that clemency should form any part of the court’s consideration. The question was whether there was something in the conduct of the action or the circumstances of the case which took the case out of the norm in a way which justified an order for indemnity costs.

The judge did not accept that the combination of the Claimant’s tactics and the Claimant’s expert approaching the case in a more technical rather than practical manner, then effectively going off on a frolic of his own immediately before trial and not giving the evidence expected during his oral evidence, created circumstances to justify an order for indemnity costs. It was of relevance that the expert evidence timetable was “concertina-ed” into a short time frame before trial. The joint expert report became available about three months before trial and the individual expert reports then followed. Supplementary expert reports were filed because of additional factors raised in the various reports which required a reply. The judge did not find in the circumstances of this case that the conduct of the Claimant’s lawyers was such that the action was conducted, or the circumstances were such, that it was out of the norm in a way which justified an order for indemnity costs.

Payment on account

The parties were agreed that a payment on account of costs should be made. Applying the principles in MacInnes v Gross [2017] 4 WLR 49, the Defendant sought £312,700.75, being the approved budget in the sum of £344,082, less 10% bringing that sum down to £309,673.80 and then adding interest at 4% of £12,386.96, payable within 21 days. The Claimant sought a reduction of 20% to take into account the fact that there was not a mediation which had been part of the budgeted costs. The Defendant objected to further reduction as the budgeted figure was for all forms of ADR. There was no justification to consider individual phases to reduce further. Any adjustment could be dealt with at detailed assessment.

The judge held that the starting point for assessment of a reasonable sum was a 10% reduction. She did not accept that it was reasonable or proportionate to increase the percentage reduction further in this case. Mediation did not take place, but other forms of ADR did. Interest would run on the costs payable. The judge accepted that 4% interest on pre-judgment costs was a reasonable percentage. She awarded interim costs in the sum of £309,673.80 plus interest at 4%.

YouTube player

 

Refusal To Mediate Does Not Always Justify Indemnity Costs

Failure To Engage In ADR And Indemnity Costs, Again

Part 36 Validity, Protocol Breaches And Mediation Timing In Probate Disputes

CPR 44.2(8) | Payments On Account In Costs Budgeted Cases

Successful Defendant’s Costs In Judicial Review Claim Reduced by 15% for Partial Failure On Discreet Issue

CPR 44.2 And The Courts’ Discretion As To Costs

 

The King’s Bench Division’s decision in Full Colour Black Limited v Banksy [2026] EWHC 795 (KB) addresses the costs consequences following discontinuance of libel proceedings which the court found had been pursued to exert improper pressure rather than to obtain vindication by adjudication.

Background

Full Colour Black Limited, trading as Brandalised (“FCB”), is a company established in 2007 whose business model centres on the commercialisation of contemporary street art, including works attributed to Banksy. Andrew Gallagher is FCB’s sole director and shareholder. He began photographing Banksy’s art in 2001 and subsequently, through FCB, began exploiting those works commercially by granting licences to reproduce photographs of the artworks on clothing, greeting cards and related merchandise.

Banksy is an internationally renowned pseudonymous street artist who has consistently sought to preserve his anonymity. The Second Defendant, Pest Control Office Limited, is a registered company that publicly describes itself as the parent and legal guardian for Banksy. It holds an exclusive worldwide licence of the copyright in Banksy’s artworks and acts as his sole approved authentication body. Consistent with Banksy’s publicly stated opposition to the commercial exploitation of his works, neither Banksy nor Pest Control licences his images to third parties for commercial purposes.

The relationship between FCB and the Defendants had been fractious for well over a decade before these proceedings were commenced. The Defendants had repeatedly objected to FCB’s activities on copyright grounds, and FCB had repeatedly resisted those objections whilst simultaneously seeking to persuade Banksy to enter into a commercial arrangement. Notably, in correspondence dating back to November 2011 and again in January 2014, Mr Gallagher had drawn attention to the risk that litigation would expose Banksy to public identification, given that he would be required to give evidence to establish authorship and ownership of copyright. Those communications were accompanied by proposals for confidential commercial discussions. Aaron Wood, a Chartered Trade Mark Attorney who acted for FCB, made a series of public statements to similar effect, including comments to the BBC, the Daily Telegraph, and Australian television, all of which acknowledged that Banksy faced a fundamental dilemma: pursuing copyright litigation would require him to reveal his identity.

FCB’s business model was, as the court noted, legally precarious. A photograph of an artwork may attract its own copyright, but that does not displace the copyright in the underlying artistic work. Reproducing photographs of Banksy’s works on merchandise without a licence from the copyright owner carried an inherent risk of infringement proceedings. FCB had no such licence.

The immediate trigger for the libel proceedings was a collaboration between FCB and the fashion retailer GUESS, which launched a clothing collection in October 2022 marketed as “GUESS X BRANDALISED WITH GRAFFITI BY BANKSY”. The collection featured images derived from Banksy’s works, including the well-known “Flower Thrower”. No permission had been sought from or granted by Banksy or Pest Control. On 18 November 2022, Banksy posted a photograph of the Regent Street GUESS store window on his Instagram account, accompanied by the following message: “Attention all shoplifters. Please go to GUESS on Regent Street. They’ve helped themselves to my artwork without asking, how can it be wrong for you to do the same to their clothes?” The post attracted widespread public and media attention and led to crowds gathering outside the store, its temporary closure, and the removal of the “GRAFFITI BY BANKSY” wording from the window display.

On 21 December 2022, FCB sent a formal letter of claim to the Defendants alleging that the Instagram post was defamatory. A Claim Form was issued on 6 September 2023 and served on 13 September 2023. The Particulars of Claim alleged that the post conveyed the meaning that FCB had stolen Banksy’s artwork by licensing images to GUESS without permission or other legal authority, and that publication had caused serious harm to FCB’s reputation and serious financial loss within the meaning of section 1 of the Defamation Act 2013. Significantly, the final sentence of paragraph 2 of the Particulars of Claim included a purported reservation of the right to seek an order requiring Banksy to identify himself for the purposes of the proceedings.

Following service of Acknowledgments of Service in September 2023, FCB’s solicitors objected to Banksy’s failure to state his full name in the Acknowledgment of Service, relying on CPR 10.5(1)(d). On 4 October 2023, an article was published in The Sun in which Mr Wood was quoted commenting that “the worst thing that could happen to Banksy is if he gets unmasked by appearing in court”. On 10 October 2023, the Defendants’ solicitors provided a substantive response, admitting responsibility for publication of the Instagram post, denying that it was defamatory, and advancing defences of truth and qualified privilege. That letter also addressed the anonymity issue and foreshadowed a formal application for anonymity.

On 22 November 2023, the Defendants issued an application seeking an order that Banksy’s real identity be withheld and that he be referred to only as “Banksy” in the proceedings (“the Identity Application”), together with an extension of time for service of a Defence. The matter was referred to Nicklin J, who on 8 December 2023 made an order, without a hearing, giving directions for the Identity Application and directing FCB to issue any application seeking an order that Banksy identify himself by 5 January 2024, failing which the relevant sentence in the Particulars of Claim would be struck out. The order also required FCB to explain what it sought to achieve against Banksy that it could not legitimately achieve against the Second Defendant alone.

FCB did not pursue the naming application. On 28 February 2024, by consent, the court stayed the claim against Banksy pending resolution of the claim against the Second Defendant and confirmed the striking out of the reservation of rights sentence. The Identity Application was resolved by consent order on 12 March 2024, granting Banksy anonymity pursuant to CPR 39.2(4).

The Second Defendant served its Defence on 26 January 2024. Notably, the Defence did not advance a defence of honest opinion, despite that having been foreshadowed in earlier correspondence. FCB served its Reply on 8 March 2024, in which it resiled from its earlier case on publication and declined to admit that Banksy was the creator of the relevant artworks, requiring the Second Defendant to prove those matters. The Defendants characterised this as a tactical shift intended to maintain the risk that Banksy might be required to give evidence.

FCB then took no steps in the litigation for over a year. On 4 February 2025, the Second Defendant issued an application for summary judgment and/or striking out of the claim. FCB instructed new solicitors in February 2025, who engaged in without prejudice save as to costs correspondence seeking to settle not only the libel proceedings but also wider matters between the parties, including trade mark disputes, and proposing a broader “co-existence” commercial arrangement. The Defendants rejected that approach. On 27 March 2025, before the summary judgment application was determined, FCB served a Notice of Discontinuance.

On 22 July 2025, the Defendants issued an application seeking: (1) an order that FCB pay their costs on the indemnity basis; (2) a non-party costs order against Mr Gallagher personally; and (3) a payment on account of costs. The application was heard by Nicklin J on 28 November 2025, with judgment handed down on 1 April 2026.

Legal Principles

Indemnity costs

When a claim is discontinued, CPR 38.6(1) provides that the claimant is liable for the defendant’s costs on the standard basis. The court may, however, make a different order.

In Thakkar v Mican [2024] 1 WLR 4196, the Court of Appeal summarised the key principles governing indemnity costs orders. To obtain indemnity costs, the receiving party must surmount a “high hurdle” by demonstrating “some conduct or some circumstance which takes the case out of the norm”. Where the application is based on the paying party’s conduct, it is necessary to show that such conduct was “unreasonable to a high degree”, though it is not necessary to demonstrate “a moral lack of probity or conduct deserving of moral condemnation”. The phrase “out of the norm” reflects something outside the ordinary and reasonable conduct of proceedings.

In Hosking v Apax Partners LLP [2019] 1 WLR 3347, the Court of Appeal considered indemnity costs following discontinuance. The court held that discontinuance does not of itself justify an assessment of the merits, nor does it ordinarily require the court to determine whether the claim was unwarranted. However, the court is entitled to examine the circumstances of the case at the point of discontinuance, including the documentary record and the manner in which the proceedings were pursued, to assess whether the claim lacked real vitality or was continued as a means of extracting a settlement.

A hallmark of cases falling “out of the norm” is that proceedings have been high-risk litigation pursued, and often deliberately publicised, to exert pressure in the hope of extracting a settlement, with frail evidential support and little regard to their prospects of success at trial or any genuine objective of securing vindication by adjudication. Although such conduct may not amount to an abuse of process in strict terms, the court may have been intentionally used as an instrument of leverage – an “anvil for settlement” – rather than as an adjudicator. Where such conduct is demonstrated, discontinuance should not deter, and may positively incline, the court towards an award of indemnity costs.

Non-party costs orders

The jurisdiction to make a non-party costs order derives from section 51 of the Senior Courts Act 1981. In Dymocks Franchise Systems (NSW) Pty Ltd v Todd [2004] 1 WLR 2807, the House of Lords held that the ultimate question is whether, in all the circumstances, it is just to make the order. Where a non-party not only funds but also substantially controls proceedings, or stands to benefit from them, justice will ordinarily require that if the proceedings fail, the non-party should bear the successful party’s costs. In such cases, the non-party may properly be characterised as the “real party” to the litigation.

Where the proposed non-party is a director or shareholder of a corporate litigant, the authorities emphasise the fundamental importance of limited liability. In Goknur Gida Maddeleri Enerji Imalet Ithalat Ihracat Tiracet ve Sanayi AS v Aytacli [2021] 4 WLR 101, the Court of Appeal held that control of the litigation, even sole control, is not of itself sufficient to justify a non-party costs order against a director. The touchstone is whether the director can fairly be described as “the real party to the litigation”. To persuade a court to make such an order, the applicant will usually need to establish either that the director was seeking to benefit personally from the company’s pursuit of the litigation, or that he or she was guilty of serious impropriety or bad faith. Such impropriety or bad faith must be of a serious nature and will ordinarily need to be causatively linked to the applicant unnecessarily incurring costs.

The Indemnity Costs Application

The Defendants limited their application to costs incurred from 10 October 2023, the date on which they provided their substantive response to the claim and formally raised the issue of protection of Banksy’s anonymity. They contended that the litigation was deployed as a means of exerting improper pressure by exploiting Banksy’s well-known and long-standing desire to preserve his anonymity. They relied on the history of threats made by FCB, the repeated acknowledgement that Banksy faced a risk of being unmasked if he became embroiled in legal proceedings, FCB’s early procedural steps and pleadings which raised the prospect of identifying Banksy, and the repeated linkage drawn between that issue and FCB’s commercial demands.

The Defendants further relied on the timing of FCB’s discontinuance, which occurred only when FCB was confronted with a substantive challenge to the viability of its case and the imminent incurring of further costs. That sequence, they submitted, supported the inference that the proceedings were abandoned once they ceased to be an effective means of applying pressure.

FCB resisted any award of indemnity costs. It submitted that the claim was properly brought to vindicate its reputation and was always arguable. It emphasised that discontinuance does not, without more, justify indemnity costs and that parties must be free to discontinue when litigation is no longer proportionate or commercially sensible. FCB denied that the proceedings were pursued for any improper or ulterior purpose and submitted that there was no strategy to threaten or procure the unmasking of Banksy. It relied on the fact that it did not pursue a naming application and ultimately accepted a stay of the claim against Banksy as being inconsistent with any alleged impropriety.

The Court’s Analysis on Indemnity Costs

Nicklin J held that the case fell outside the norm and that FCB must pay the Defendants’ costs on the indemnity basis from 10 October 2023. His conclusion did not rest on discontinuance alone, nor did it depend upon a finding that FCB was not entitled to discontinue when it did. It was founded on the manner and purpose for which the proceedings were pursued, viewed objectively and in the round.

The court found that, on the material before it, the defamation claim was, viewed objectively, without any real prospect of success. In particular, once the relevant context was taken into account, an honest opinion defence would, in all likelihood, have disposed of the claim. The court noted that honest opinion was “far and away the strongest defence” and that its omission from the Defence was otherwise difficult to understand. The most likely explanation was that reliance on that defence was recognised to carry an increased risk that Banksy would be required to give evidence, with the attendant risk of identification.

The critical feature which explained why such a claim was nonetheless pursued, and what took the case outside the norm, was that the proceedings were deployed to exert pressure relying upon Banksy’s well-known concern to preserve his anonymity as central to his artistic expression. The court referred to the history of communications in which Mr Gallagher drew attention to the risk to Banksy’s anonymity inherent in litigation and sought to use that risk as leverage in disputes concerning the commercial exploitation of Banksy’s works.

That dynamic was also reflected in the conduct of the litigation. The inclusion in the Particulars of Claim of a purported reservation of a right to seek an order requiring Banksy to identify himself, the subsequent correspondence pressing for Banksy’s “full name”, and the pleading decisions which had the effect of maintaining the possibility that Banksy might ultimately be required to give evidence, were not incidental to the procedural course adopted. Taken cumulatively, they served to maintain and to some extent to amplify the very risk which the court later took steps to contain by case management and anonymity orders.

A further consideration reinforced that conclusion. At an early stage of the proceedings, the Second Defendant admitted responsibility for publication of the Instagram post. In circumstances where the Second Defendant had done so, and having regard to the remedies sought by FCB, there was little objective justification for naming Banksy as a personal defendant. The decision nevertheless to include Banksy as a defendant from the outset, and to maintain his presence in the proceedings until compelled by case management to do otherwise, was consistent with the conclusion that FCB deliberately exposed Banksy to the risk inherent in the proceedings that his anonymity might be jeopardised, and that this was intended to exert pressure rather than to secure remedies which could not adequately be obtained against the Second Defendant alone.

The court rejected Mr Gallagher’s evidence that the proceedings were brought for vindication of legal rights in defamation. It reached that conclusion because it was inconsistent with the objective documentary record and with the inherent logic of the position which FCB adopted. A claim which, viewed objectively, had no real prospect of succeeding by adjudication was difficult to reconcile with a purely vindicatory purpose; whereas it was readily explicable if the proceedings were regarded as creating leverage by reason of the continuing sensitivity around Banksy’s anonymity.

The court made a further distinct finding regarding the honest opinion defence. Viewed in the context of the proceedings as a whole, the continuation of the proceedings could be understood as proceeding on the basis that Banksy would be reluctant to take procedural or evidential steps which might increase the risk of identification, even if those steps were otherwise available. The absence of an honest opinion defence was consistent with that analysis.

The correspondence in March 2025, marked without prejudice save as to costs, provided further support. FCB’s settlement overtures were not confined to compromise of the defamation proceedings. They were framed to link settlement to wider matters and to the prospect of a broader “co-existence” or commercial arrangement under which FCB would be permitted to continue exploiting Banksy’s works. Whilst not sufficient on its own, it provided support to the conclusion that the proceedings were being used, at least in part, to seek a broader commercial accommodation rather than to obtain vindication by adjudication.

Finally, the timing of the discontinuance – in the face of a substantive challenge and the prospect of further significant costs – was consistent with the inference that the proceedings were abandoned once they ceased to serve the function for which they were being deployed. No other explanation had been offered by FCB as to the sudden decision to discontinue.

Taking these matters together, the court was satisfied that the proceedings were pursued in a manner and for purposes which were unreasonable to a high degree and which took the case outside the norm. The Defendants’ limitation of their application to costs incurred from 10 October 2023 was appropriate and proportionate. Although FCB’s plan to exploit the Defendants’ concerns over Banksy’s anonymity was implemented when the Claim Form was issued and Particulars of Claim drafted, 10 October 2023 was the date on which the Defendants provided their substantive response to the claim and formally raised the issue of protection of Banksy’s anonymity in the proceedings.

The Non-Party Costs Application

The Defendants submitted that Mr Gallagher was the driving force behind the litigation, exercised complete control over it, and stood to benefit personally from its outcome. In those circumstances, they argued, he should properly be regarded as the real party to the proceedings. Alternatively, they submitted that Mr Gallagher’s conduct met the threshold of serious impropriety required to justify a non-party costs order, relying on the same features of the litigation conduct said to justify indemnity costs.

Mr Gallagher submitted that the principles governing non-party costs orders against directors and shareholders are stringent and deliberately so, reflecting the fundamental importance of limited liability. He accepted that he controlled the litigation, but submitted that control, even when combined with sole ownership, is not sufficient to justify a non-party costs order. He denied that he was the real party to the litigation in the relevant sense, submitting that the claim was brought to vindicate the company’s asserted commercial and reputational interests, and that any benefit to him was no more than the indirect consequence of his shareholding. He further denied any serious impropriety or bad faith on his part.

The Court’s Analysis on the Non-Party Costs Application

Nicklin J refused the application for a non-party costs order against Mr Gallagher. The court held that the application raised a distinct and more exacting question than the indemnity costs application. The issue was not whether the litigation was conducted in a manner which justifies an indemnity costs order against a company, but whether it is just to impose personal liability for costs on a person who was not a party to the proceedings, thereby displacing the principle of limited liability.

The court was satisfied that the two jurisdictions are distinct and that the thresholds are not co-extensive. While the same facts may be relevant to both applications, a finding sufficient to justify indemnity costs does not automatically or necessarily justify a non-party costs order. A separate and more exacting analysis is required before displacing the principle of limited liability.

An indemnity costs order is concerned with marking, in costs, litigation conduct which is unreasonable to a high degree or otherwise outside ordinary and reasonable forensic behaviour. It does not require a finding of dishonesty or moral turpitude. By contrast, where the proposed non-party is a director/shareholder of a corporate litigant, control of the litigation – even sole control – and even the pursuit of litigation which is ill-advised or tactically motivated will not ordinarily suffice. Something more is required: either that the director be properly characterised as the “real party” to the litigation in the relevant sense, or that the director’s personal conduct involves serious impropriety or bad faith of a qualitatively different order from ordinary litigation misjudgment or tactical opportunism.

Mr Gallagher plainly exercised control over the litigation as FCB’s sole director and shareholder. The court also accepted that he was, in a practical sense, the directing mind of the company and that the conduct which it had found to take the case outside the norm for the purposes of indemnity costs reflected decisions taken under his direction. However, the law draws a deliberate distinction between responsibility for litigation conduct which warrants an indemnity costs order against a corporate party, and the exceptional step of imposing personal liability for costs under section 51 of the Senior Courts Act 1981.

In the present case, whilst Mr Gallagher plainly controlled the litigation, the court was not satisfied that he was the “real party” to it in the requisite sense. The claim was brought in the company’s name and sought relief for the company, namely vindication of asserted corporate reputational and commercial interests and recovery of alleged corporate loss. Any personal advantage to Mr Gallagher from a successful outcome would have been indirect and incidental to his shareholding. That is not unusual in the case of a small company whose shares are held by, and whose affairs are controlled by, a single director, and does not, without more, justify treating the director as the true litigant and transferring to him the company’s costs liability.

The court also took into account that FCB was advised by solicitors and Counsel. The litigation strategy adopted was formulated and implemented with the benefit of legal advice, albeit directed towards objectives which the court had found to be improper for the purposes of the indemnity costs analysis. That feature did not excuse the company’s conduct, but it was relevant to whether it is just to impose personal liability on the director in the absence of clearer evidence that he acted in bad faith of the kind contemplated by the authorities. The court was not satisfied that any aspect of Mr Gallagher’s personal conduct provided a sufficient causative basis for transferring to him personal responsibility for costs arising from the company’s prosecution of the claim.

The Defendants also relied on the allegedly precarious financial position of FCB as supporting the inference that Mr Gallagher was using the company’s corporate personality to shield himself personally from the costs consequences of litigation. The court was unable to draw that inference on the evidence before it. While there was material suggesting that FCB’s financial position deteriorated significantly after publication of the Instagram post, the court did not have sufficient evidence as to the company’s financial health at the time when the litigation strategy was adopted and pursued, or as to whether FCB was then insolvent, undercapitalised, or being rendered unable to meet an adverse costs order by design.

Nor was the court persuaded that the evidence established serious impropriety or bad faith by Mr Gallagher personally of the qualitatively different order required to justify a non-party costs order. The court had found that the proceedings were deployed to exert pressure. However, the evidence did not establish, to the requisite standard, that Mr Gallagher engaged in dishonesty towards the court, deliberate manipulation of the corporate form to render the company unable to meet an adverse costs order, or other conduct of a markedly different order from aggressive or opportunistic litigation strategy. In short, the conduct warranted the sanction of an indemnity costs order against the corporate claimant, but it did not cross the higher threshold required to make it just to impose personal costs liability on Mr Gallagher.

The court also took into account the delay in bringing the non-party costs application which, while not determinative, reinforced the conclusion that it would not be just to make such an order.

Conclusion

FCB was ordered to pay the Defendants’ costs from 10 October 2023 on the indemnity basis. The application for a non-party costs order against Mr Andrew Gallagher was refused. FCB must make a payment on account of costs in a sum to be determined.

Indemnity Basis Costs Following Discontinuance

Non Party Costs Orders | Court Of Appeal Decision

Dishonest Evidence And Baseless Allegations Justify Indemnity Costs Order

CPR 38.6: Discontinuance And Costs – The Legal Principles

Understanding Non-Party Costs Orders

Director Ordered To Pay Creditor’s Costs Personally Despite Rule 3.4 In Failed Administration Application

 

The Senior Courts Costs Office’s decision in Tucker & Anor v Howe [2026] EWHC 208 (SCCO) addresses two consequential issues arising from a nine-day detailed assessment of the costs of an estate administrator appointed under probate proceedings.

Background

The matter concerned the detailed assessment of costs under section 71(3) of the Solicitors Act 1974. The costs were those of Mr Mark Keeley, a solicitor and partner at Freeths LLP, who had been appointed as administrator pending suit of the estate of the late Mr Steven Howe. The appointment was made by order of HHJ Pearce on 16 October 2020 within probate proceedings brought by the executrices (the Claimants) to propound Mr Howe’s will against his daughter, the Defendant. Mr Keeley’s appointment authorised him to charge reasonable professional fees and terminated upon the final order in the probate claim.

The probate claim was compromised by a consent order in December 2021. Disputed matters of administration were later resolved by a further consent order made by District Judge Woodward on 21 February 2023. That order provided for the determination of the Administrator’s costs by way of a third-party detailed assessment pursuant to section 71(3) of the 1974 Act, setting out a timetable for the service of a bill, points of dispute, and the commencement of assessment proceedings in the Senior Courts Costs Office if agreement was not reached. The bill for assessment, served pursuant to that order, was drawn in the total sum of £147,436.33 across twelve parts, covering both contentious and non-contentious work under two separate contracts of retainer, together with Mr Keeley’s own professional time costs and counsel’s fees.

The assessment hearing took nine days of court time over three separate periods between April 2024 and February 2025. That duration was largely the result of 67 pages of Points of Dispute which employed the word “staggering” or “staggeringly” 54 times and the word “astonishing” 17 times. The court found none of that hyperbole justified. The bill was assessed at £129,686.76, just below 88% of the amount claimed. The court found the Claimants’ conduct to have been unreasonable to a high degree and ordered them to pay the costs of the assessment on the indemnity basis, summarily assessed at £132,400 exclusive of VAT.

The parties were unable to agree the terms of a final order, leading to a further hearing on two unresolved issues: whether the Claimants or the estate should bear the costs of the assessment, and the recoverability of VAT on those assessment costs. The question of costs liability had taken on particular significance because the estate of Mr Howe was insolvent, an Insolvency Administration Order having been made on 23 July 2025.

Costs Issues Before the Court

Two discrete costs issues required determination. The first was the identity of the party liable to pay the costs of the detailed assessment proceedings. The Claimants argued the burden should fall on the insolvent estate, while Mr Keeley contended the Claimants were personally liable in their capacity as beneficiaries who had applied for the assessment. The second issue was whether Value Added Tax was properly recoverable on the costs of the assessment, with the Claimants arguing that the work constituted a non-taxable self-supply by Freeths.

The Parties’ Positions

On the burden of costs, Professor Watson-Gandy submitted for the Claimants that the central consideration in a section 71(3) assessment was the protection of the estate’s interests, relying on Kenig v Thomson Snell & Passmore LLP [2024] EWCA Civ 15. He argued that the Claimants had participated in their capacity as executrices fulfilling a fiduciary duty to the beneficiaries. He submitted that DJ Woodward’s consent order made no provision for personal liability and that CPR 46.2, which governs costs orders against non-parties, would have been required if such liability was intended.

Mr Latham argued for Mr Keeley that the Claimants had clearly applied for and pursued the assessment in their capacity as beneficiaries, a point reinforced by their own pre-action correspondence and by the legal arguments they had advanced to broaden the scope of the assessment. The Claimants’ representative, Mr Valls, had consistently corresponded on behalf of all the beneficiaries and demanded a detailed assessment in that capacity. The court retained an absolute discretion under section 51 of the Senior Courts Act 1981 and section 71(3)(b) of the 1974 Act. Given the court’s findings on the Claimants’ unreasonable conduct — conduct not attributable to the estate or the beneficiaries as a whole — it was appropriate to order the Claimants to pay the costs personally.

On VAT, Professor Watson-Gandy argued that where solicitors act for themselves in contentious business matters, the supply is not a taxable supply, citing the VAT tribunal decisions in Ralph Arthur Archer v The Commissioners and D A Walker v The Commissioners. It was submitted that Freeths’ bills were addressed to Mr Keeley at Freeths, and that estate accounts bore Freeths’ business address, indicating a self-supply. Mr Latham submitted that the point had not been raised in the Points of Dispute against the main bill and should not be permitted to be raised after the assessment had concluded. On the merits, he argued that Mr Keeley and Freeths were separate legal entities capable of entering into a retainer and that VAT was properly chargeable on Freeths’ supply of services to him.

The Court’s Decision

Burden of the Costs of Assessment

Costs Judge Leonard held that the Claimants were personally liable for the assessment costs in their capacity as beneficiaries. The court rejected the argument that they had acted as executrices, for several reasons. The Claimants had made it clear from the outset that they were acting as beneficiaries. They had relied extensively upon their position as beneficiaries to broaden the scope of their challenges to Mr Keeley’s costs. And the statutory jurisdiction under section 71(3) does not empower the court to order an assessment on the application of a trustee, executor or administrator; it empowers the court to do so on the application of any person interested in the relevant property — in this case, the beneficiaries of Mr Howe’s will.

The description of the Claimants as executrices in the heading of the proceedings and other procedural documents reflected the proper title of the probate proceedings in which the consent order was made. It had no bearing on the substance of the order or the capacity in which the assessment was pursued. The court held that CPR 46.2 had no application because the Claimants were already parties to the assessment proceedings, not non-parties. DJ Woodward’s order made no provision for the costs of the assessment because orders for assessment do not make such provision; the award and quantification of those costs was a matter for the assessing judge.

Even if the court was wrong on any of those points, it accepted Mr Latham’s submissions on the appropriate exercise of discretion. The Claimants had, without ever themselves making any attempt at negotiation, rejected three attempts by Mr Keeley to settle the costs dispute upon receipt of a smaller sum than he was ultimately found to be due on assessment. Had they engaged with those settlement attempts, it would have been possible to avoid the necessity for the court to spend nine days reducing the bill by less than £18,000 inclusive of VAT. It would be unfair for the estate, and potentially for Mr Ross Tucker and Mr Jamie Tucker (who did not participate in the assessment), to bear any part of the burden of the unnecessary costs incurred through the Claimants’ actions.

Recoverability of VAT

The court first held that the Claimants were barred from raising a VAT challenge to the main bill itself, having failed to raise the point in their Points of Dispute. CPR 47.14(6) provides that only items specified in the points of dispute may be raised at the hearing unless the court gives permission, and no such permission had been sought or granted.

On the substantive question of VAT on the costs of the assessment, the court found no basis for the self-supply argument. Mr Keeley and Freeths LLP are separate entities capable of entering into a contract of retainer. Freeths had provided services to Mr Keeley under two contracts of retainer, and VAT was payable on their charges in the usual way. The termination of Mr Keeley’s appointment as administrator did not affect this analysis. On Mr Keeley’s own time costs (Part 10 of the bill), the court held there was no question of self-supply because his services as administrator were supplied to the estate, not to himself. As for the costs of the assessment, Mr Keeley had been represented by counsel instructed by Freeths; he was not representing himself. He had a liability to Freeths for the attendant costs, and they had an obligation to add VAT to their fees and disbursements. The inclusion of Freeths’ address on bills or estate accounts was not to the point.

YouTube player

Summary Assessment Without Opposition | Court Applies Independent Scrutiny to Unopposed Costs Claims

Provisional Assessment Set Aside Under CPR 3.1(7) For Material Breach Of Filing Duty

When A Judicial Review Claim Is Discontinued | Can The Defendant Recover Costs Beyond The Acknowledgment Of Service Stage?

Part 36 Offers Cannot Displace The Solicitors Act One-Fifth Costs Rule

CPR 26.9(10)(e) | Wrongful Interference With Goods Against Police Mandates Multi-Track Allocation | Part 36 Acceptance Does Not Oust Fixed Costs

Does Removal As Trustee Always Mean Loss Of Indemnity?